Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
3/2/2020
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
3/2/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Propane Tank
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Gas Line: Exterior
|
|
Date Completed:
|
| | |
1/13/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Gas Line: Interior
|
|
Date Completed:
|
| | |
1/13/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Revised Bldg Pmt (F)
|
|
Date Completed:
|
| | |
10/10/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
9/26/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
10/4/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
10/7/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initiate Revision
|
|
Date Completed:
|
| | |
9/24/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Invoice for DCD Sent
|
|
Date Completed:
|
| | |
6/13/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
6/11/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
3/2/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
3/2/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Fire Protection
|
|
Date Completed:
|
| | |
3/2/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Wallboard Nailing
|
|
Date Completed:
|
| | |
12/13/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Insulation: Ceiling
|
|
Date Completed:
|
| | |
12/11/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Insulation: Floors
|
|
Date Completed:
|
| | |
12/11/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Insulation: Walls
|
|
Date Completed:
|
| | |
12/11/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Rough-in Plumbing
|
|
Date Completed:
|
| | |
12/11/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Underground Plumbing
|
|
Date Completed:
|
| | |
9/24/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
3/2/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Post Holes
|
|
Date Completed:
|
| | |
7/12/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Setbacks
|
|
Date Completed:
|
| | |
7/12/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
6/7/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Potable Water Approval
|
|
Date Completed:
|
| | |
3/28/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
3/22/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
3/22/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
3/19/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
DRD Approval (Zoning)
|
|
Date Completed:
|
| | |
5/16/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Public Works Approval
|
|
Date Completed:
|
| | |
5/16/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Planning Approval
|
|
Date Completed:
|
| | |
5/16/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic System Finaled
|
|
Date Completed:
|
| | |
2/26/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
6/7/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
5/16/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
5/16/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
3/19/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
5/1/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
3/19/2019
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
5/17/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
3/19/2019
|
|
Disposition:
|
| | |
DONE
|
|