Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
2/8/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
1/15/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Drywell/Alt Drainage
|
|
Date Completed:
|
| | |
5/7/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Change Status to RENEWED
|
|
Date Completed:
|
| | |
1/29/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Inspection Reminder Sent (1st)
|
|
Date Completed:
|
| | |
12/18/2019
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Foundation Footing
|
|
Date Completed:
|
| | |
3/22/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Revised Bldg Pmt (F)
|
|
Date Completed:
|
| | |
3/20/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Drywell/Alt Drainage
|
|
Date Completed:
|
| | |
3/20/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
3/20/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initiate Revision
|
|
Date Completed:
|
| | |
3/20/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
3/20/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Footing Drains
|
|
Date Completed:
|
| | |
3/6/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Foundation Stem Wall
|
|
Date Completed:
|
| | |
2/26/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
1/25/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
1/24/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initiate Revision
|
|
Date Completed:
|
| | |
1/24/2019
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
2/8/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Smoke & CO
|
|
Date Completed:
|
| | |
1/15/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Blower Airtight Test
|
|
Date Completed:
|
| | |
2/8/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Wallboard Nailing
|
|
Date Completed:
|
| | |
4/28/2020
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Int. Shear Wall Nailing
|
|
Date Completed:
|
| | |
8/20/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Insulation: Ceiling
|
|
Date Completed:
|
| | |
10/3/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Insulation: Walls
|
|
Date Completed:
|
| | |
10/3/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Straps (hold downs)
|
|
Date Completed:
|
| | |
9/12/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Airseal
|
|
Date Completed:
|
| | |
9/12/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
9/12/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Shower Pan
|
|
Date Completed:
|
| | |
1/15/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Rough-in Plumbing
|
|
Date Completed:
|
| | |
7/12/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Ext. Shear Wall Nailing
|
|
Date Completed:
|
| | |
6/27/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Insulation: Floors
|
|
Date Completed:
|
| | |
3/27/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Underground Plumbing
|
|
Date Completed:
|
| | |
3/12/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Foundation Footing
|
|
Date Completed:
|
| | |
2/20/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Setbacks
|
|
Date Completed:
|
| | |
2/20/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Address Posted
|
|
Date Completed:
|
| | |
1/15/2021
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
12/12/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic System Finaled
|
|
Date Completed:
|
| | |
6/25/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
1/25/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Address Review Complete
|
|
Date Completed:
|
| | |
1/10/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
12/18/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
12/18/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
1/10/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
12/18/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
1/10/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Potable Water Approval
|
|
Date Completed:
|
| | |
12/14/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
12/12/2018
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
1/24/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
12/18/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
MEDIUM STORMWATER
|
|
Wording
|
| | |
The applicant is proposing to create or add 3566 square feet of impervious surface and 5156 square feet of land disturbing activities. JCC 18.30.060 and 18.30.070 require the project applicant submit a stormwater plan meeting Minimum Requirements #1 through #5 of the Department of Ecology Stormwater Management Manual for Western Washington. The stormwater plan shall address measures to control stormwater, erosion and sediment during construction and shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
STORMWATER PLAN
|
|
Wording
|
| | |
A Stormwater Plan has been submitted and approved by the Department of Community Development. Once the subject permit has been issued the applicant shall fully implement the provisions of the submitted plan. No clearing for roadways or utilities shall occur on the project site until clearing necessary for the installation of temporary sedimentation and erosion control measures have been completed. Site restoration presented in the plan must include removing invasive species and re-planting native varaties of under cover.
|
|
|
Title:
|
| | |
CONFIRMED ESA'S
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on December 18, 2018 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review, the following ESAs were confirmed to be present on the subject property: Coastal SIPZ
|
|
|
Title:
|
| | |
COASTAL SIPZ
|
|
Wording
|
| | |
The parcel is located within a coastal SIPZ (seawater intrusion protection zone) according to the County GIS map. There are voluntary and mandatory measures identified in the Jefferson County Seawater Intrusion Policy (Resolution 61-02, effective September 23, 2002) that apply to well drilling proposals and building permit applications on existing lots of record.
|
|
|
Title:
|
| | |
APPROVAL FOR NSFR ONLY
|
|
Wording
|
| | |
This approval is for a new single family residence only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
PLANNER
|
|
Wording
|
| | |
scc
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
Septic Sizing
|
|
Wording
|
| | |
This building approval accounts for 240 GPD of septic system capacity, as designed and approved SEP07-00066 is sized for only one single family residence. It is not sized for an Accessory Dwelling Unit (ADU). The minimum daily design flow per residence is 240 GPD.
|
|
|
Title:
|
| | |
Water line/Septic system setback
|
|
Wording
|
| | |
10' minimum separation required between the water line and any onsite sewage system components including sewage transport lines.
|
|
|
Title:
|
| | |
Water line/Septic system setback
|
|
Wording
|
| | |
10' minimum separation required between the water line and any onsite sewage system components including sewage transport lines.
|
|
|
Title:
|
| | |
Septic - Stormwater setbacks
|
|
Wording
|
| | |
SEPTIC SYSTEM COMPONENT SETBACKS TO STORMWATER MANAGEMENT FACILITIES -
Any interceptor/curtain drain or foundation drain, or any other source of water that is downgradient or below MUST be setback a minimum of 30’ from any septic system dispersal area (drainfield) and 5’ from any septic tanks.
Splash blocks must be directed away from ALL septic components.
Subsurface stormwater infiltration, subsurface soil dispersal systems with NO discharge point must be located a minimum of 10 ft. downgradient of the drainfield.
|
|