Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
8/16/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Wallboard Nailing
|
|
Date Completed:
|
| | |
7/19/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
7/2/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
1/19/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
12/18/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Additional Info Request-EH
|
|
Date Completed:
|
| | |
1/19/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Wallboard Nailing
|
|
Date Completed:
|
| | |
7/17/2018
|
|
Disposition:
|
| | |
FAIL
|
|
|
Description:
|
| | |
Insp - Insulation: Ceiling
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Insulation: Walls
|
|
Date Completed:
|
| | |
7/10/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
6/18/2018
|
|
Disposition:
|
| | |
FAIL
|
|
|
Description:
|
| | |
Insp - Straps (hold downs)
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Foundation Footing
|
|
Date Completed:
|
| | |
5/3/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Setbacks
|
|
Date Completed:
|
| | |
5/3/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
8/25/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
8/25/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic System Finaled
|
|
Date Completed:
|
| | |
8/14/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Address Review Complete
|
|
Date Completed:
|
| | |
8/25/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
8/25/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
8/25/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
8/25/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
8/25/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
8/25/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
9/26/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
1/19/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
8/25/2017
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
8/25/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
PLANNER
|
|
Wording
|
| | |
DWJ
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
NO PLUMBING REVWD OR APPRVD
|
|
Wording
|
| | |
No plumbing has been reviewed or approved for this project by Jefferson County Public Health. Additional requirements may apply if plumbing is proposed.
|
|
|
Title:
|
| | |
Water line/Septic system setback
|
|
Wording
|
| | |
10' minimum separation required between the water line and any onsite sewage system components including sewage transport lines.
|
|
|
Title:
|
| | |
Septic Inspection
|
|
Wording
|
| | |
ADDITIONAL SEPTIC SYSTEM INSPECTION REQUIRED PRIOR TO FINAL APPROVAL of this building permit. The septic system permitted under SEP17-00212 must be completed.
|
|
|
Title:
|
| | |
Septic - Stormwater setbacks
|
|
Wording
|
| | |
SEPTIC SYSTEM COMPONENT SETBACKS TO STORMWATER MANAGEMENT FACILITIES -
Any interceptor/curtain drain or foundation drain, or any other source of water that is downgradient or below MUST be setback a minimum of 30’ from any septic system dispersal area (drainfield) and 5’ from any septic tanks.
Splash blocks must be directed away from ALL septic components.
Subsurface stormwater infiltration, subsurface soil dispersal systems with NO discharge point must be located a minimum of 10 ft. downgradient of the drainfield.
|
|