Case Number:BLD2015-00234 Case Status:Finaled Date Received:7/9/2015
Description:Replace 3 antennas, remove 3 TMA'S install, 3 FRLB radios, 2 FXFC, 1 FXFC, 1 FBBC, 1FSMR and 1 ESMB. Revision- relocate 1 existing microwave- 1 new microwave- Remove 1 existing platform- Install 3 new antenna mounts. Date Issued:7/21/2015
Applicant:T-MOBILE WEST LLC CROWN CASTLE Expiration Date:7/21/2017 12:00:00 AM
Site Address:2805 LARSON LAKE RD Case Finaled:7/3/2017
Parcel No:801122002 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Insp - FINAL FINAL Building
Date Completed: 7/3/2017
Disposition: DONE
Description: Override - Parcel Holds
Date Completed: 7/3/2017
Disposition:
Description: Insp - Final Building
Date Completed:
Disposition:
Description: Inspection Reminder Sent (2nd)
Date Completed: 6/23/2017
Disposition:
Description: Inspection Reminder Sent (1st)
Date Completed: 5/30/2017
Disposition:
Description: Change Status to RENEWED
Date Completed: 7/21/2016
Disposition: DONE
Description: Inspection Reminder Sent
Date Completed: 6/23/2016
Disposition: DONE
Description: DCD Review Time
Date Completed: 3/24/2016
Disposition:
Description: Issue Revised Bldg Pmt (F)
Date Completed: 3/24/2016
Disposition: DONE
Description: Override - Parcel Holds
Date Completed: 3/24/2016
Disposition:
Description: DCD Review Time
Date Completed: 3/23/2016
Disposition:
Description: Up Front Review
Date Completed: 3/24/2016
Disposition: DONE
Description: Building Permit Application(F)
Date Completed: 3/9/2016
Disposition: DONE
Description: Override - Parcel Holds
Date Completed: 3/9/2016
Disposition:
Description: Consistency Review-U
Date Completed: 3/23/2016
Disposition: DONE
Description: Plan Check
Date Completed: 3/11/2016
Disposition: DONE
Description: Initiate Revision
Date Completed: 3/9/2016
Disposition: DONE
Description: Issue Building Permit (F)
Date Completed: 7/21/2015
Disposition: DONE
Description: Override - Parcel Holds
Date Completed: 7/21/2015
Disposition:
Description: A Clock Interrupt
Date Completed:
Disposition:
Description: A Clock Interrupt
Date Completed: 7/21/2015
Disposition: DONE
Description: Insp - Miscellaneous
Date Completed: 7/3/2017
Disposition: DONE
Description: Up Front Review
Date Completed: 7/20/2015
Disposition: DONE
Description: Building Permit Application(F)
Date Completed: 7/9/2015
Disposition: DONE
Description: Override - Parcel Holds
Date Completed: 7/9/2015
Disposition:
Description: Building Permit Application(F)
Date Completed: 7/9/2015
Disposition: DONE
Description: Override - Parcel Holds
Date Completed: 7/9/2015
Disposition:
Description: Override - Parcel Holds
Date Completed: 7/9/2015
Disposition:
Description: Override - Parcel Holds
Date Completed: 7/9/2015
Disposition:
Description: DRD Approval (Zoning)
Date Completed: 7/15/2015
Disposition: DONE
Description: Final Planning Approval
Date Completed: 7/15/2015
Disposition: DONE
Description: Consistency Review-U
Date Completed: 7/14/2015
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 7/14/2015
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 7/14/2015
Disposition: DONE
Description: Contractor License/Bond Info
Date Completed: 7/21/2015
Disposition: DONE
Description: Plan Check
Date Completed: 7/17/2015
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 7/14/2015
Disposition: DONE
Description: Case Entered
Date Completed: 7/9/2015
Disposition:

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: APPROVAL FOR REV TO TOWER MOD ONL
Wording The approval granted July 14, 2015 was to replace three antennas, remove 3 TMA's, install 3 FRLB radios, 2FXFC, 1 FXMF, and 1 FBBC, 1 FSMR and 1 ESMB. This revision approval is to relocate one existing microwave, add one new microwave, remove one existing platform and install three new antenna mounts only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.

Title: SITE PLAN CHANGES
Wording The revised site plan as submitted with the cell tower modification application on March 7, 2016 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved revised site plan dated March 23, 2016 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: PLANNER
Wording EDB

Title: NOISE COMPLIANCE
Wording The installed permitted equipment will be compliant with Jefferson County Code 18.42.090 (g). T-Mobile will be responsible for not exceeding the maximum environmental noise levels set forth in WAC Chapter 173-60.

Title: WIRELESS FACILITY EXEMPTION
Wording The proposal meets JCC18.42.020(2)(d) which exempts the following from the provisions of the Chapter 18.42 JCC. Emergency or routine repairs, reconstruction, or routine maintenance of previously approved facilities, or replacement of transmitters, antennas, or other components of previously approved facilities which do not create a change in visual impact.

Title: BMPs