Description:
|
| | |
Certificate of Occupancy-F
|
|
Date Completed:
|
| | |
6/2/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
5/27/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Rough-in Plumbing
|
|
Date Completed:
|
| | |
5/16/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
5/16/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Ext. Shear Wall Nailing
|
|
Date Completed:
|
| | |
5/16/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
5/13/2016
|
|
Disposition:
|
| | |
FAIL
|
|
|
Description:
|
| | |
Insp - Foundation Footing
|
|
Date Completed:
|
| | |
4/20/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Revised Bldg Pmt (F)
|
|
Date Completed:
|
| | |
3/31/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
12/17/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
3/28/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
3/28/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
3/28/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
3/28/2016
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
3/24/2016
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Insulation: Ceiling
|
|
Date Completed:
|
| | |
5/19/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Insulation: Floors
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Insulation: Walls
|
|
Date Completed:
|
| | |
5/19/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Rough-in Plumbing
|
|
Date Completed:
|
| | |
5/13/2016
|
|
Disposition:
|
| | |
FAIL
|
|
|
Description:
|
| | |
Insp - Foundation Footing
|
|
Date Completed:
|
| | |
4/18/2016
|
|
Disposition:
|
| | |
FAIL
|
|
|
Description:
|
| | |
Insp - Setbacks
|
|
Date Completed:
|
| | |
4/18/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
3/8/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
3/2/2016
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Potable Water Approval
|
|
Date Completed:
|
| | |
3/9/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
3/8/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
3/28/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
3/14/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Initiate Revision
|
|
Date Completed:
|
| | |
3/2/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
5/27/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
12/17/2015
|
|
Disposition:
|
| | |
FAIL
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
7/31/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
5/23/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Up Front Review
|
|
Date Completed:
|
| | |
7/29/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
6/16/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
6/4/2015
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
5/27/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Parking
|
|
Date Completed:
|
| | |
5/27/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Smoke & CO
|
|
Date Completed:
|
| | |
5/27/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Wallboard Nailing
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
FAIL
|
|
|
Description:
|
| | |
Insp - Int. Shear Wall Nailing
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Ext. Shear Wall Nailing
|
|
Date Completed:
|
| | |
5/13/2016
|
|
Disposition:
|
| | |
FAIL
|
|
|
Description:
|
| | |
Insp - Straps (hold downs)
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Additional Info Request-EH
|
|
Date Completed:
|
| | |
6/8/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-PW
|
|
Date Completed:
|
| | |
7/29/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
7/29/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
5/1/2015
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Address Review Complete
|
|
Date Completed:
|
| | |
7/31/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
7/28/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
7/10/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
5/4/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
5/4/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
7/31/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
6/2/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
4/30/2015
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
6/8/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
6/8/2015
|
|
Disposition:
|
| | |
DONE
|
|