Description:
|
| | |
Certificate of Occupancy-F
|
|
Date Completed:
|
| | |
12/7/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
12/7/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
12/7/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Blower Airtight Test
|
|
Date Completed:
|
| | |
12/8/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Up Front Review
|
|
Date Completed:
|
| | |
4/16/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
4/15/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
4/15/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Smoke & CO
|
|
Date Completed:
|
| | |
12/7/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Wallboard Nailing
|
|
Date Completed:
|
| | |
9/8/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
12/4/2015
|
|
Disposition:
|
| | |
FAIL
|
|
|
Description:
|
| | |
Insp - Address Posted
|
|
Date Completed:
|
| | |
12/7/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Int. Shear Wall Nailing
|
|
Date Completed:
|
| | |
7/17/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Insulation: Ceiling
|
|
Date Completed:
|
| | |
11/25/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Insulation: Floors
|
|
Date Completed:
|
| | |
6/12/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Insulation: Walls
|
|
Date Completed:
|
| | |
9/1/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Airseal
|
|
Date Completed:
|
| | |
8/27/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Framing
|
|
Date Completed:
|
| | |
8/27/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Rough-in Plumbing
|
|
Date Completed:
|
| | |
8/6/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Ext. Shear Wall Nailing
|
|
Date Completed:
|
| | |
7/24/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Underground Plumbing
|
|
Date Completed:
|
| | |
7/17/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Foundation Stem Wall
|
|
Date Completed:
|
| | |
7/17/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Footing Drains
|
|
Date Completed:
|
| | |
6/5/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Foundation Footing
|
|
Date Completed:
|
| | |
5/13/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Setbacks
|
|
Date Completed:
|
| | |
5/13/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
3/17/2015
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic System Finaled
|
|
Date Completed:
|
| | |
11/25/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Address Review Complete
|
|
Date Completed:
|
| | |
4/15/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
4/15/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
3/18/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
3/18/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
3/18/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
3/17/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
3/30/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Potable Water Approval
|
|
Date Completed:
|
| | |
3/27/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
3/17/2015
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
3/27/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
3/18/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
PLANNER
|
|
Wording
|
| | |
DWJ
|
|
|
Title:
|
| | |
STREAM BUFFER
|
|
Wording
|
| | |
Applicant and Home Owner shall maintain a 100 foot buffer from Chimacum Creek.
|
|
|
Title:
|
| | |
Do Not Disturb Buffer
|
|
Wording
|
| | |
All construction activities shall not encroach upon the Stream buffer. This includes the storage or preparation of materials.
|
|
|
Title:
|
| | |
Identify Streamside Buffer
|
|
Wording
|
| | |
A permanent physical separation along the boundary of the buffer area shall be installed and permanently maintained. Such separation can include installing logs, trees, a hedgerow, or any other prominent physical marking approved by the UDC Administrator.
|
|
|
Title:
|
| | |
Mark Stream During Construction
|
|
Wording
|
| | |
Buffer perimeters shall be marked with temporary signs at an interval of one per parcel or every one hundred (100) feet, whichever is less. Signs shall be in place prior to and during construction activities. The signs shall contain the following statement: "Buffer - Do Not Remove or Alter Existing Vegetation."
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
Water line/Septic system setback
|
|
Wording
|
| | |
10' minimum separation required between the water line and any onsite sewage system components including sewage transport lines.
|
|