Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
5/6/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
5/6/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
5/6/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Inspection Reminder Sent
|
|
Date Completed:
|
| | |
4/6/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
5/28/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Foundation Stem Wall
|
|
Date Completed:
|
| | |
5/28/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Setbacks
|
|
Date Completed:
|
| | |
5/28/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
5/6/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
5/6/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
DRD Review Complete-U
|
|
Date Completed:
|
| | |
3/26/2015
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
3/26/2015
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
12/10/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Up Front Review
|
|
Date Completed:
|
| | |
12/2/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
12/2/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
11/19/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Straps (hold downs)
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Foundation Footing
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
7/29/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
DRD Approval (Zoning)
|
|
Date Completed:
|
| | |
12/2/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Address Review Complete
|
|
Date Completed:
|
| | |
8/20/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
11/19/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
11/19/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
11/19/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
7/29/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
8/12/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
7/29/2014
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
12/9/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
LANDSCAPING - FINDING
|
|
Wording
|
| | |
The proposed 10 x 18 vaporizers' pad and 2 piers to reset an exisitng 9,000 gallon tank is within the mill site and adjacent to the mill access road. Existing vegetation on the site is adequate to satisfy the landscaping requirements of the Jefferson County Code; therefore, no landscaping will be required.
|
|
|
Title:
|
| | |
SITE PLAN CHANGES
|
|
Wording
|
| | |
The site plan as submitted with the proposed 10' x 18' vaporizers' pad and 2 piers to reset an existing 9,000 gallon tank application on July 9, 2014 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated March 27, 2015 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
APPROVAL FOR ________ ONLY
|
|
Wording
|
| | |
This approval is for a new 10' x 18' vaporizors' pad and 2 piers to reset and exisging 9,000 gallon tank only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
STORMWATER - FINDING
|
|
Wording
|
| | |
The proposed 10' x 18' pad and 2 piers will not provide additional impervious surface; therefore, no further stormwater provisions will be required.
|
|
|
|
Title:
|
| | |
SETBACKS
|
|
Wording
|
| | |
The setbacks shall be measured from the edge of the right-of-way, which is 30.5 feet from the centerline of the as-built Mill Roaed right-of-way (See letter frm Johnston Land Surveying dated 11-6-14 and affirmed by Will Butterfield of Jefferson County Public Works Department in his email dated 11-13-14 attached to the file). Setbacks shall meet the minimum standards of the Uniform Fire Code and the International Building Code.
|
|