Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
11/6/2019
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
CANCEL BUILDING PERMIT
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
EXPIRED PERMIT
|
|
Date Completed:
|
| | |
9/19/2018
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Change Status to RENEWED
|
|
Date Completed:
|
| | |
7/3/2017
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
7/3/2017
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
EXPIRED PERMIT
|
|
Date Completed:
|
| | |
1/1/1900
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Inspection Reminder Sent
|
|
Date Completed:
|
| | |
9/2/2016
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
8/31/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
8/27/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Return Status to Pending
|
|
Date Completed:
|
| | |
8/26/2015
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
8/26/2015
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
6/18/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Miscellaneous Action
|
|
Date Completed:
|
| | |
6/18/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
6/17/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
DRD Reviewer Letter (F)
|
|
Date Completed:
|
| | |
6/1/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
5/13/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
3/19/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
3/16/2015
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
DCD Review Time
|
|
Date Completed:
|
| | |
12/31/2014
|
|
Disposition:
|
| | |
PEND
|
|
|
Description:
|
| | |
Updated/Add'l Info Recv'd
|
|
Date Completed:
|
| | |
12/29/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-EH
|
|
Date Completed:
|
| | |
5/13/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
DCD Review Time
|
|
Date Completed:
|
| | |
9/29/2014
|
|
Disposition:
|
| | |
PEND
|
|
|
Description:
|
| | |
Additional Info Request-DRD
|
|
Date Completed:
|
| | |
4/6/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
DCD Review Time
|
|
Date Completed:
|
| | |
7/28/2014
|
|
Disposition:
|
| | |
PEND
|
|
|
Description:
|
| | |
DCD Review Time
|
|
Date Completed:
|
| | |
5/27/2014
|
|
Disposition:
|
| | |
PEND
|
|
|
Description:
|
| | |
Additional Info Request-BLD
|
|
Date Completed:
|
| | |
3/19/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
4/6/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
A Clock Interrupt
|
|
Date Completed:
|
| | |
5/27/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
8/27/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
2/6/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Planning Approval
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
5/27/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
6/17/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
5/27/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
5/27/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
6/17/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
2/20/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
5/13/2015
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
2/7/2014
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
BATHROOM CLOSURE CONTINGENCY
|
|
Wording
|
| | |
The approval by JCPH is based on the signed agreement by Ed Girard, SW Region Manager WSP, that the comfort station shall be connected to the sewage system prior to beginning any excavation in the vicinity of the drainfields. If it is not connected to an approved and operable sewage treatment plant the building will be closed/locked until connection is complete and the treatment system is approved to operate. The signed agreement was received via email April 9, 2015.
|
|
|
Title:
|
| | |
HOLD-DRAINFIELD MATERIAL
|
|
Wording
|
| | |
The material that is removed from the drainfield that has come into contact with waste water must be treated/decontaminated prior to final disposal. The material from the system shall be removed and stockpiled to allow for pathogen die-off. The material shall be placed in 6"-8" lifts and spread with lime. The location for the stockpile shall be approved by the Health Officer and shall meet all requirements of an onsite sewage system (setbacks from surface waters and wells and vertical separation). It shall be covered and protected from erosion (covered with plastic or several inches of uncontaminated soil and straw, etc.). After the material has been stockpiled for a minimum of one year, the material may be used without site restrictions.
|
|
|
Title:
|
| | |
HOLD-EXISTING SEPTIC TANKS
|
|
Wording
|
| | |
The septic tanks associated with the drainfields (case number SEP79-00289) that are being decommissioned may be retained for emergency storage in case of a power failure of the new MBR wastewater treatment system. The tanks shall be permanently capped prior to removal of the drainfields from the area.
|
|
|
Title:
|
| | |
HOLD-INSPECTION-DRAINFIELD SPOILS
|
|
Wording
|
| | |
HOLD - Jefferson County Public Health shall be notified prior to moving the drainfield spoils and placement in the treatment area. An inspection by JCPH is required to verify compliance with the conditions of placement of the soils and lime.
|
|
|
Title:
|
| | |
NO SHOOTING AREA
|
|
Wording
|
| | |
This parcel is within a no shooting area per JCC 8.50.
|
|
|
Title:
|
| | |
FEMA BIOP CONDITION
|
|
Wording
|
| | |
This project is subject to the FEMA Biological Opinion. Federal approvals are issued if the project complies with the Endangered Species Act. To address the Biological Opinion, the applicant shall adhere to all conditions in the permit issued by the U.S. Army Corps of Engineers. Work on this project shall not begin until a federal permit has been issued.
|
|
|
Title:
|
| | |
ZONING CONDITION
|
|
Wording
|
| | |
The parcel has been designated as Parks, Preserves, and Recreation (PPR) under the Jefferson County Comprehensive Land Use Map effective August 28, 1998. Recreational facilities are an allowed use in this zoning designation (Table 3-1, JCC).
|
|
|
Title:
|
| | |
PLAN SHEETS CONDITION
|
|
Wording
|
| | |
The applicant shall implement the proposal based on sheets received by DCD on March 16, 2015, including the stormwater pollution prevention plan, the general construction notes, and the planting plan.
|
|
|
Title:
|
| | |
SITE PLAN CHANGES CONDITION
|
|
Wording
|
| | |
The site plan, as submitted with the building application on March 16, 2015, has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated June 1, 2015 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
APPROVAL FOR _____ ONLY CONDITION
|
|
Wording
|
| | |
This approval is for a bridge replacement with stream improvements only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|
|
Title:
|
| | |
SHORELINE CONDITION
|
|
Wording
|
| | |
This project was reviewed and approved as a shoreline exemption under JCC 18.25.090(19).
|
|
|
Title:
|
| | |
GEOTECH CONDITION
|
|
Wording
|
| | |
A geotechnical report prepared by Krazan and Associates (dated April 27, 2015) was submitted on May 5, 2015. The applicant shall adhere to all recommendations in this report, including having the project geologist onsite during bridge construction.
|
|
|
Title:
|
| | |
Follow Flood Ordinance
|
|
Wording
|
| | |
Flood hazard reduction measures are to be used as required by the Jefferson County Flood Damage Prevention Ordinance 07-0515-06 (Jefferson County Code Chapter 15.15).
|
|
|
Title:
|
| | |
Res Construction Flood Damage
|
|
Wording
|
| | |
Construction Materials and Methods of Construction to Reduce Flood Hazard:
(i) All new construction and substantial improvements shall be constructed with materials and utility equipment resistant to flood damage; and
(ii) All new construction and substantial improvements shall be constructed using methods and practices that minimize flood damage.
|
|
|
Title:
|
| | |
GEOTECH CERTIFICATION
|
|
Wording
|
| | |
PRIOR TO ISSUING A FINAL BUILDING CERTIFICATE OF OCCUPANCY, PROPONENT SHALL SUBMIT A WRITTEN LETTER FROM THE GEOLOGIST WHO PREPARED THE GEOTECHNICAL REPORT DATED APRIL 27, 2015 STATING THAT THE STRUCTURE AND/OR FACILITIES HAVE BEEN CONSTRUCTED IN CONFORMANCE WITH THE REQUIREMENTS OF THE "GEOTECHNICAL REPORT." THE LETTER SHALL BE STAMPED BY THE LICENSED GEOLOGIST/ENGINEER.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
Comply with HPA
|
|
Wording
|
| | |
In addition to Jefferson County permit conditions, the project proponent shall comply with all conditions set forth by the Washington Department of Fish and Wildlife through Hydraulic Project Approval.
|
|
|
Title:
|
| | |
Army Corps Check
|
|
Wording
|
| | |
Prior to commencing development activity, the proponent is responsible for informing the US Army Corps of Engineers (COE) in order for COE to determine whether a Department of the Army permit or review is required. Generally, review is required for construction and dredging in or around navigable waters of the US and for work or fill in hydrologically connected wetlands. Contact the US Army Corps of Engineers, Seattle District Regulatory Branch, PO Box 3755, Seattle WA 98124, (206) 764-3495, for more information.
|
|
|
Title:
|
| | |
HOLD-DECOMMISSION DRAINFIELD
|
|
Wording
|
| | |
H - The drainfields will be decommissioned and the soils removed to an area inspected and approved by JCPH on April 24, 2015. The area for disposal and treatment of the drainfield spoils is on the south side of the area known as Group Camp #1. The area is protected by a large rock barrier and no entry signs due to unstable trees on a steep slope to the south of the area. Additional signage shall be added to assure that visitors and campers do not access the area. Signage shall read 'Soil Treatment area - Do Not Enter' or similar.
|
|
|
Title:
|
| | |
F-SHORELINE FINDING
|
|
Wording
|
| | |
This proposal will be conducted within shoreline jurisdiction (floodplain of the Dosewallips River) and the shoreline designation of the Dosewallips River is Conservancy. This is an approval to restore fish habitat along Twana Creek and the proposal complies with JCC 18.25.090(19).
|
|
|
Title:
|
| | |
F-HPA Issued
|
|
Wording
|
| | |
The Washington Department of Fish and Wildlife issued Hydraulic Project Approval (HPA) for this activity on December 9, 2013 under Control Number 132315-1. The HPA expires on September 30, 2016.
|
|
|
Title:
|
| | |
F-DNS Issued
|
|
Wording
|
| | |
Reviewed under the State Environmental Policy Act (SEPA) by Washington State Parks and Recreation Commission acting as lead agency. A Determination of Non-Significance (DNS) issued on October 7, 2013.
|
|
|
Title:
|
| | |
F-General PMT Notice
|
|
Wording
|
| | |
NOTICE: This permit does not excuse the proponent from complying with other local, state, and federal ordinances, regulations, or statutes applicable to the proposed development, but consistent with RCW 90.58.
Development pursuant to this permit shall be undertaken subject to the applicable policies and performance standards of the Jefferson County Shoreline Management Master Program and the Jefferson County Unified Development Code.
If during excavation or development of the site an area of potential archaeological significance is uncovered, all activity in the immediate area shall be halted, and the Administrator shall be notified at once.
The Federal Endangered Species Act rules to protect threatened Chinook and Summer-run Chum salmon became effective on January 8, 2001. Bull trout have been listed as threatened since early 2000. Under the ESA, any person may bring lawsuit against any individual or agency that "takes" listed species (defined as causing harm, harassing, or damaging habitat for the listed species). In addition, the National Marine Fisheries Service can levy penalties. Portions of Jefferson County, including marine environments are included as "critical habitat" for listed species. Development of property along any marine shoreline, freshwater shoreline, or floodplains could harm habitat if protective measures are not taken. To minimize the potential to damage habitat, all property owners developing adjacent to marine shoreline, freshwater shoreline, or floodplains are advised to do the following:
- All development activities should avoid unstable slopes, wetlands, and forested areas near surface waters
- Remove minimal vegetation for site development, especially large trees
- Allow trees that have fallen into surface waters to remain there
- Infiltrate stormwater from buildings and driveways onsite through drywells rather than discharging directly into surface waters or roadside ditches
The Federal Bald and Golden Eagle Protection Act requires landowners within 660 feet (1/8th of a mile) of an eagle nest to consult with the US Fish and Wildlife Service. This Eagle Act prohibits anyone from "taking" bald eagles. This federal law defines the term "take" and describes the possible legal consequences when a "take" occurs. Among other actions, "take" includes a disturbance of bald eagles or their habitat. Under federal law a permit may still be required for activities that impact bald eagles or their habitat. Contact the US Fish and Wildlife Service (http://www.fws.gov/pacific/eagle/) to learn more about how this law affects your project.
Any individual, group, or agency can bring suit for a listed species "taking", even if you are in compliance with Jefferson County development codes. The risk of a lawsuit against you can be reduced by consulting with a professional fisheries habitat biologist, and following the recommendations for site development provided by the biologist. For more information, contact the National Marine Fisheries Service in Seattle, or the U.S. Fish and Wildlife Service.
|
|