Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
10/6/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
9/14/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
9/15/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
9/13/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
10/27/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
10/26/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print Dummy UDC Permit-UF
|
|
Date Completed:
|
| | |
10/26/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
10/26/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Miscellaneous
|
|
Date Completed:
|
| | |
9/14/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
9/30/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
9/15/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
9/30/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
9/15/2005
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
10/20/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
10/20/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
9/30/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
9/30/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
10/26/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
9/30/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Bld Setbacks
|
|
Wording
|
| | |
Minimum setback frm Church Ln right-of-way is 20 ft. Minimum side and rear setbacks are 5 ft.
|
|
|
Title:
|
| | |
Bld lot coverage
|
|
Wording
|
| | |
Maximum lot coverage is not to exceed 25%. Lot coverage is defined as amount of impervious surface which includes roof tops, driveways, concrete, etc.
|
|
|
Title:
|
| | |
HEALTH APPROVAL
|
|
Wording
|
| | |
This Health approval for a temporary use as a preschool is granted based on the letter from the school operators stating use of the facilities for the school for a maximum of 3 yrs for one preschool-kindergarten class of no more than 12 children and 2 teachers.
|
|
|
Title:
|
| | |
WATER USE
|
|
Wording
|
| | |
Water use shall be monitored weekly for the first 2 months and monthly thereafter. Results shall be submitted to the Health Department quarterly.
|
|
|
Title:
|
| | |
C-NO CHANGE TO STRUCTURE
|
|
Wording
|
| | |
This proposal will be utilizing existing structure, parking, lightings, drainage and alike. No alteration or changes to these improvements are proposed.
|
|
|
Title:
|
| | |
C-COMPLIANCE WITH STATE LICENSING
|
|
Wording
|
| | |
Applicants shall demonstrate compliance with state licensing requirements of a Child Day Care Facilities.
|
|
|
Title:
|
| | |
Aquifer Recharge Conditions (SFR)
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
F-ZON
|
|
Wording
|
| | |
This parcel has been designated as Rural Residential 1:5 under the Jefferson County Comprehensive Plan Land Use Map effective August 28, 1998.
|
|
|
Title:
|
| | |
F-ASSESSORY USE
|
|
Wording
|
| | |
The Administrator determined this proposal is an accessory use as it is sited on the premises of an existing community services use per UDC 4.18.1.d(1).
|
|
|
Title:
|
| | |
F-PARKING
|
|
Wording
|
| | |
The Administrator has determined the proposal will not create additional need for parking in excess of that currently provided on-site. Generally most church activities occur on the weekend or during the evening hours. The preschool will be in session from 9:30am to 1:30pm on Mondays through Thursdays. Parents will be carpooling and using public transportation. Those using the parking lot will only need to park for a short time as they drop off or pick up children. Teachers will use at most two (2) spaces for the duration of the morning.
|
|
|
Title:
|
| | |
F-OFF-STREET DROP OFF
|
|
Wording
|
| | |
Applicants are proposing to utilize the existing parking lot for vehicles to drop off and pick up children.
|
|
|
Title:
|
| | |
F-ACCESS
|
|
Wording
|
| | |
Church Ln (P608) is a private road. The road approach is existing and address of 130 Church Ln has been assigned to the parcel.
|
|
|
Title:
|
| | |
F-CASE HISTORY
|
|
Wording
|
| | |
1. Conditional Use Permit (ZON02-00167) was approved October 31, 2003 for construct up to 28 bedrooms of housing for seniors, families, individuals and persons with disabilities. A binding site plan has also been submitted for purposes of subdivisiing off the south 7.5 acres of the parcel that will be utilized for the housing development proposal.
2. A sign permit (ZON00-00028) was finaled November 16, 2000 and the associated building permit (BLD00-00586) was finaled November 8, 2000.
3. A septic permit (SEP85-00166) was finaled April 11, 1986.
|
|
|
Title:
|
| | |
F-NO SIGN
|
|
Wording
|
| | |
No sign was proposed with this application. Any future sign proposal shall require review for consistency with applicable codes and ordinances.
|
|
|
Title:
|
| | |
F-ZONING
|
|
Wording
|
| | |
The applicant is proposing to utilize one room for preschool with maximum 12 children at the existing Community United Methodist Church. The property is also known as Lot 1 of South 7 Village Binding Site Plan, recorded on July 26, 2004 under AFN 487342. The property contains sufficient parkings and existing landscaping.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on September 30, 2005 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Susceptible Aquifer Recharge Areas and Special Aquifer Recharge Protection Areas.
|
|
|
Title:
|
| | |
F-Aquifer Recharge Area
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.
|
|
|
Title:
|
| | |
F-Susc. Aquifer Recharge Area
|
|
Wording
|
| | |
Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.
|
|
|
Title:
|
| | |
F-Critical Aquifer Recharge Area
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas are defined as Seawater Intrusion Areas, and Special Aquifer Recharge Protection Areas and the following land uses located within Susceptible Aquifer Recharge Areas (1) All Industrial Land Uses (2) All Commercial Uses (3) All Rural Residential Land Uses requiring a Discretionary Use or Conditional Use Permit (4) All Rural Residential Land Uses with nonconforming uses that would otherwise require a Discretionary Use or Conditional Use Permit (5) Unsewered Planned Rural Residential Developments (6) Unsewered residential development with gross densities greater than one unit per acre. All of the above listed uses shall be subject to the applicable requirements and standards of the Jefferson County Unified Development Code.
|
|
|
Title:
|
| | |
F-Stormwater
|
|
Wording
|
| | |
All structures and improvements already exist. The applicant is not proposing any additional impervious surface or land disturbing activities. If land disturbing activity is proposed, Sections 6.6 and 6.7 of the Jefferson County Unified Development Code requires that your proposal shall adhere to Best Managment Practices (BMPs).
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(b)(iii).
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The revised site plan as submitted on October 20, 2005 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated October 21, 2005 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-APPROVAL FOR PRESCHOO ONLY
|
|
Wording
|
| | |
This approval is for a preschool with maximum 12 children at the existing Community United Methodist Church facility only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|