Case Number:BLD2005-00275 Case Status:Finaled Date Received:5/3/2005
Description:NEW SFR W/ CARPORT & A/G 250 GALLON PROPANE TANK Date Issued:6/6/2005
Applicant:GREGORY HARE Expiration Date:6/6/2007 12:00:00 AM
Site Address:522 TOTEM RIDGE RD Case Finaled:3/8/2006
Parcel No:901114028 Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: Certificate of Occupancy-F
Date Completed: 3/9/2006
Disposition: DONE
Description: Insp - FINAL FINAL Building
Date Completed: 3/8/2006
Disposition: DONE
Description: Insp - Final Building
Date Completed: 3/8/2006
Disposition: DONE
Description: Insp - Final Building
Date Completed:
Disposition:
Description: File Archived
Date Completed: 1/27/2006
Disposition:
Description: Insp - Insulation: Walls
Date Completed: 11/7/2005
Disposition: DONE
Description: Insp - Airseal
Date Completed: 11/2/2005
Disposition: DONE
Description: Insp - Framing
Date Completed: 11/2/2005
Disposition: DONE
Description: Insp - Rough-in Plumbing
Date Completed: 11/2/2005
Disposition: DONE
Description: Insp - Shear Wall Nailing
Date Completed: 10/20/2005
Disposition: DONE
Description: Insp - Miscellaneous
Date Completed: 10/18/2005
Disposition: DONE
Description: Insp - Shear Wall Nailing
Date Completed: 10/18/2005
Disposition: FAIL
Description: Insp - Miscellaneous
Date Completed: 8/23/2005
Disposition: DONE
Description: Insp - Foundation Stem Wall
Date Completed: 8/15/2005
Disposition: DONE
Description: Change Status to RENEWED
Date Completed: 8/9/2005
Disposition: DONE
Description: Insp - Foundation Footing
Date Completed: 8/3/2005
Disposition: DONE
Description: Insp - Setbacks
Date Completed: 8/3/2005
Disposition: DONE
Description: Issue Building Permit (F)
Date Completed: 6/6/2005
Disposition: DONE
Description: Approve Permit-UF
Date Completed: 5/27/2005
Disposition: DONE
Description: Print Dummy UDC Permit-UF
Date Completed: 5/27/2005
Disposition: DONE
Description: Review Complete-U
Date Completed: 5/27/2005
Disposition: DONE
Description: Additional Info Request-U
Date Completed: 5/27/2005
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 5/24/2005
Disposition: DONE
Description: Application Received-UF
Date Completed: 5/9/2005
Disposition: DONE
Description: Building Permit Application(F)
Date Completed: 5/3/2005
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 5/24/2005
Disposition: DONE
Description: Case Entered
Date Completed: 5/3/2005
Disposition:
Description: Plan Check
Date Completed: 5/20/2005
Disposition: DONE
Description: Septic Review Complete-U
Date Completed: 5/10/2005
Disposition: DONE
Description: Potable Water Approval
Date Completed: 5/6/2005
Disposition: DONE
Description: Contractor License/Bond Info
Date Completed: 5/4/2005
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 5/27/2005
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 5/27/2005
Disposition: DONE
Description: Consistency Review-U
Date Completed: 5/27/2005
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 5/12/2005
Disposition: DONE

Case Conditions
Below is a list of conditions for this permit case. Conditions typically record requirements that the applicant must meet to be in compliance with the permit.
Title: Bld Security/hooded lights
Wording Lighting fixtures shall be designed and hooded to prevent the light source from being directly visible from outside the boundaries of the property. The intensity or brightness of all lighting, during construction and after project completion shall not adversely affect the use of surrounding properties or adjoining rights-of-way.

Title: Bld Exterior height lights
Wording Exterior lighting for residential uses shall not exceed twenty feet (20') in height from the finished grade, excepting when such lighting is an integral part of a building or structure. Ground level lighting is encouraged.

Title: Bld Setbacks
Wording Setback from Totem Ridge Rd. right-of-way is no less than 20 ft., side and rear setbacks are no less than 5 ft. If an environmentally sensitive area (ESA) is present, then the more restrictive setback shall apply.

Title: Bld building height
Wording The building height is not to exceed 35 feet.

Title: Bld lot coverage
Wording Maximum lot coverage is not to exceed 25%. Lot coverage is defined as amount of impervious surface which includes roof tops, driveways, concrete, etc.

Title: Outdoor Residential Storage
Wording Outdoor residential storage shall be maintained in an orderly manner and shall create no fire, safety, health or sanitary hazard.

Title: Unlicensed/Inoperable Vehicles
Wording Not more than two (2) unlicensed or inoperable vehicles shall be stored on any lot less than one-half acre unless totally screened from view of neighboring dwellings and rights-of-way. Such screening shall meet all applicable performance and development standards specific to the district in which the storage is kept, and shall be in keeping with the character of the area. Screening shall meet the requirements of Unified Development Code (UDC) Section 6. Outdoor storage of thirteen (13) or more unlicensed or inoperable vehicles is prohibited except in those districts where specified as an automobile wrecking yard or junk (or salvage) yard and allowed as a Permitted Use in Table 3-1 of the UDC, and such storage shall meet the requirements of UDC Section 4.10. In no case, shall any such unlicensed or inoperable vehiclesbe stored in an Environmentally Sensitive Area (ESA).

Title: PARKING
Wording A minimum of two (2) on-site parking spaces is required for the single-family residence.

Title: STORMWATER ON SITE
Wording Stormwater shall be retained and infiltrated on site. The owner shall control all sedimentation and erosion on the property.

Title: Landslide Vegetative Buffer
Wording A vegetative buffer of 30-feet shall be permanently maintained from the top or edge of the Landslide Hazard Area. All buffers shall be measured perpendicularly from the top of the Landslide Hazard Area.

Title: Slide Buffer-Native Vegetation
Wording Landslide Hazard Areas and their associated buffers shall remain naturally vegetated. Should buffer disturbance occur during construction, the Unified Development Code (UDC) Administrator shall require replanting with native vegetation. No alterations shall be made to the Landslide Hazard Area or its associated buffer without prior authorization by the UDC Administrator.

Title: Identify Landslide Hazard Buffer
Wording Prior to and during approved construction activities, the perimeter of the landslide hazard area buffer shall be marked with a temporary sign. The sign shall be placed in such a manner that it can be directly observed from the construction area. The sign shall contain the following statement: "Landslide Hazard Area and Buffer - Do not Remove or Alter Existing Vegetation."

Title: Do Not Disturb Buffer
Wording All construction activities shall not encroach upon the buffer. This includes the storage or preparation of materials.

Title: Permanent Landslide Boundary
Wording The applicant shall permanently separate the boundary of the Landslide Hazard Area Buffer from the remainder of the subject property through installing logs, trees, a hedge row, or any other prominent physical marking approved by the UDC Administrator.

Title: BMPs
Wording The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.

Title: Stormwater Plan
Wording A Medium Stormwater Plan has been submitted and approved by the Department of Community Development. Once the subject permit has been issued the applicant shall fully implement the provisions of the submitted plan and contact the Jefferson County Department of Community Development to arrange a schedule to inspect the property for plan compliance. A Certificate of Occupancy will not be issued until the Department verifies plan compliance. No clearing for roadways or utilities shall occur on the project site until clearing necessary for the installation of temporary sedimentation and erosion control measures have been completed.


Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-ACCESS
Wording Totem Ridge Rd. (P530) is a county local access road. An address of 522 Totem Ridge has been assigned to the parcel.

Title: F-COMP PLAN
Wording This is a legal non-conforming parcel designated as Rural Residential 1:20 under the Jefferson County Comprehensive Plan Land Use Map effective August 28, 1998.

Title: F-SEPTIC
Wording A septic permit (SEP05-00068) was approved April 8, 2005 for a capacity of 480 gallons per day.

Title: F-PARCEL CREATION
Wording This parcel was created through Bruce B. Seton Short Plat under AFN 417695, recorded December 29, 1998 , Volume 4, pages 87 - 90 with the Jefferson County Auditor's office.

Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on May 24, 2005 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review, the following ESAs were confirmed to be present on the subject property: Wetlands, Landslide Hazard Area - Slight.

Title: F-Geohazard Area
Wording Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.

Title: F-Wetland Delineation Waiver
Wording The project components are more than 250' from the mapped/identified wetland. The requirement for a wetland delineation and report is waived based on maintenance of a 225' buffer from the wetland per UDC Table 3-3.

Title: F-Stormwater
Wording The applicant is proposing to create or add 4,100 square feet of impervious surface and 5,455 square feet of land disturbing activities. Sections 6.6 and 6.7 of the Jefferson County Unified Development Code requires the project applicant submit a stormwater plan meeting Minimum Requirements #1 through #5 of the Department of Ecology Stormwater Management Manual for Western Washington. The stormwater plan shall address measures to control stormwater, erosion and sediment during construction and shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.

Title: F-SEPA Exempt
Wording Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(b)(i).

Title: F-Site Plan Changes
Wording The revised site plan on May 27, 2005 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated May 27, 2005 shall be resubmitted for review and approval by Jefferson County Department of Community Development.

Title: F-APPROVAL FOR NSFR ONLY
Wording This approval is for a single-family residence with carport and a detached garage with bathroom and heated studio only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.