Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
1/26/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Building Inspection
|
|
Date Completed:
|
| | |
2/18/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Wallboard Inspection
|
|
Date Completed:
|
| | |
12/29/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insulation Inspection
|
|
Date Completed:
|
| | |
12/27/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Change Status to RENEWED
|
|
Date Completed:
|
| | |
12/14/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Framing Inspection
|
|
Date Completed:
|
| | |
12/14/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Framing Inspection
|
|
Date Completed:
|
| | |
12/14/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plumbing Inspection
|
|
Date Completed:
|
| | |
12/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Shear Wall Inspection
|
|
Date Completed:
|
| | |
12/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Change Status to RENEWED
|
|
Date Completed:
|
| | |
10/13/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Footing & Setback Inspection
|
|
Date Completed:
|
| | |
10/13/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
9/14/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
9/13/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print Dummy UDC Permit-UF
|
|
Date Completed:
|
| | |
9/13/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
9/13/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
9/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
8/27/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
8/26/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
9/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
8/26/2004
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
9/13/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
9/7/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
8/27/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
9/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
9/9/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
9/13/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
8/27/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Bld Setbacks
|
|
Wording
|
| | |
Setback should be no less than 20 ft from parcel boundary adjacent to Rhody Ct., rear setback should be no less than 5 ft, side setbacks should be no less than 5 ft.
|
|
|
Title:
|
| | |
Bld building height
|
|
Wording
|
| | |
The building height is not to exceed 35 feet.
|
|
|
Title:
|
| | |
Bld lot coverage
|
|
Wording
|
| | |
Pre-existing legal lots of record less than one acre in size in Rural Residential districts are subject to the stormwater requirements in UDC Section 6.7 and must meet the "Area of Impervious Surface Coverage" to the maximum extent practicable as determined by the Administrator." Lot coverage is defined as amount of impervious surface which includes roof tops, driveways, concrete, etc.
|
|
|
Title:
|
| | |
PARKING
|
|
Wording
|
| | |
A minimum of two (2) on-site parking spaces are required for the single family residence.
|
|
|
Title:
|
| | |
Aquifer Recharge Conditions (SFR)
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
F-ACCESS
|
|
Wording
|
| | |
Rhody Ct. (C523609) is a county road. The road approach is existing. An address of 152 Rhody Ct. has been assigned to the parcel.
|
|
|
Title:
|
| | |
F-PARCEL CREATION
|
|
Wording
|
| | |
This parcel was created through the Rhododendron Estates under AFN 371379, recorded May 2, 1994 , Volume 6, page 227 in with the Jefferson County Auditor's office.
|
|
|
Title:
|
| | |
F-COMP PLAN
|
|
Wording
|
| | |
This parcel is a legal nonconforming parcel designated as Rural Residential 1:5 under the Jefferson County Comprehensive Plan Land Use Map effective August 28, 1998.
|
|
|
Title:
|
| | |
F-CASE HISTORY
|
|
Wording
|
| | |
A septic permit (SEP95-00116) for a capacity of 360 gallons per day was finalled on January 26, 1996. A building permit (BLD95-00257) for a single family residence was finalled on February 1, 1996.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on September 8, 2004 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Susceptable Aquifer Recharge Area, Special Aquifer Recharge Protection Area.
|
|
|
Title:
|
| | |
F-Aquifer Recharge Area
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.
|
|
|
Title:
|
| | |
F-Susc. Aquifer Recharge Area
|
|
Wording
|
| | |
Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.
|
|
|
Title:
|
| | |
F-Critical Aquifer Recharge Area
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas are defined as Seawater Intrusion Areas, and Special Aquifer Recharge Protection Areas and the following land uses located within Susceptible Aquifer Recharge Areas (1) All Industrial Land Uses (2) All Commercial Uses (3) All Rural Residential Land Uses requiring a Discretionary Use or Conditional Use Permit (4) All Rural Residential Land Uses with nonconforming uses that would otherwise require a Discretionary Use or Conditional Use Permit (5) Unsewered Planned Rural Residential Developments (6) Unsewered residential development with gross densities greater than one unit per acre. All of the above listed uses shall be subject to the applicable requirements and standards of the Jefferson County Unified Development Code.
|
|
|
Title:
|
| | |
F-SMALL STORMWATER
|
|
Wording
|
| | |
The applicant is proposing to create or add 52 square feet of impervious surface and 297 square feet of land disturbing activities. Sections 6.6 and 6.7 of the Jefferson County Unified Development Code requires that your proposal comply with Minimum Requirement #2 (Construction Stormwater Pollution Prevention) of the Department of Ecology Stormwater Management Manual for Western Washington to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(b)(i).
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The site plan as submitted with the building permit application on August 25, 2004 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated September 13, 2004 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-APPROVAL FOR GARAGE ONLY
|
|
Wording
|
| | |
This approval is for a garage addition only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|