Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
1/24/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Withdrawn
|
|
Date Completed:
|
| | |
10/13/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
8/25/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
8/14/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
8/6/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
8/25/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
8/6/2003
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
8/20/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
8/13/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
10/10/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
10/10/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
8/6/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Planning Appr
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
DRD Approval (Zoning)
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Title:
|
| | |
F-Custom Universal Finding
|
|
Wording
|
| | |
This proposal is to convert an existing marina bathroom, shower facility to a hotel room. No additional impervious surface will be added and the proposal will not expand beyond the existing footprint.
|
|
|
Title:
|
| | |
F-Custom Universal Finding
|
|
Wording
|
| | |
The proposed conversion is located more than 200-feet from the Ordinary High Water Mark (OHWM) of the shoreline and will not be subject to shoreline review.
|
|
|
Title:
|
| | |
F-Custom Universal Finding
|
|
Wording
|
| | |
The proposed remodel will remove one bathroom and add one bedroom. The existing parking is adequate for the one additional room. No new landscaping will be required.
|
|
|
Title:
|
| | |
F-No ESAs Found
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development for the presence of Environmentally Sensitive Areas (ESAs). The Department conducted a review and has concluded that the property DOES NOT contain Environmentally Sensitive Areas. However, future proposals will be subject to a new ESA review and conditions may be added if new ESAs are found on the property.
|
|
|
Title:
|
| | |
F-Stormwater
|
|
Wording
|
| | |
The applicant is not proposing to create or add impervious surface. Sections 6.6 and 6.7 of the Jefferson County Unified Development Code requires that your proposal follow the Small Parcel Stormwater Plan (see attached) .
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The site plan as submitted with the building application on 9/4/03 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated 9/25/03 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for the change of an existing restroom facility to a hotel room only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|