Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
1/24/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Certificate of Occupancy-F
|
|
Date Completed:
|
| | |
7/30/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Building Inspection
|
|
Date Completed:
|
| | |
7/28/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Wallboard Inspection
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Wallboard Inspection
|
|
Date Completed:
|
| | |
1/21/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Miscellaneous inspection
|
|
Date Completed:
|
| | |
1/6/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plumbing Inspection
|
|
Date Completed:
|
| | |
12/29/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Framing Inspection
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Shear Wall Inspection
|
|
Date Completed:
|
| | |
12/17/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insulation Inspection
|
|
Date Completed:
|
| | |
9/30/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Underground Plumbing Insp.
|
|
Date Completed:
|
| | |
9/24/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Foundation Inspection
|
|
Date Completed:
|
| | |
9/12/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Change Status to RENEWED
|
|
Date Completed:
|
| | |
9/8/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Footing & Setback Inspection
|
|
Date Completed:
|
| | |
9/8/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
9/5/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
9/5/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
9/4/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-U
|
|
Date Completed:
|
| | |
8/29/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
8/26/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
8/5/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
8/1/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
8/26/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
8/1/2003
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
9/4/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
8/8/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Potable Water Approval
|
|
Date Completed:
|
| | |
8/11/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
8/4/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
9/3/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
9/3/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
9/4/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
8/1/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Bld Setbacks
|
|
Wording
|
| | |
Minimum setback from Totem Ridge Road right-of-way shall be 20 feet. Minimum north property line setback shall be 5 feet. Minimum rear (east) property line setback shall be 115 feet due to dedicated open space tract. Minimum south property line setback shall be 20 feet from Totem Ridge Road right-of-way.
|
|
|
Title:
|
| | |
Bld building height
|
|
Wording
|
| | |
The building height shall not exceed 35 feet.
|
|
|
Title:
|
| | |
Bld lot coverage
|
|
Wording
|
| | |
Maximum lot coverage shall not exceed 25%.
|
|
|
Title:
|
| | |
Outdoor Residential Storage
|
|
Wording
|
| | |
Outdoor residential storage shall be maintained in an orderly manner and shall create no fire, safety, health or sanitary hazard.
|
|
|
Title:
|
| | |
Unlicensed/Inoperable Vehicles
|
|
Wording
|
| | |
Not more than two (2) unlicensed or inoperable vehicles shall be stored on any lot less than one-half acre unless totally screened from view of neighboring dwellings and rights-of-way. Such screening shall meet all applicable performance and development standards specific to the district in which the storage is kept, and shall be in keeping with the character of the area. Screening shall meet the requirements of Unified Development Code (UDC) Section 6. Outdoor storage of thirteen (13) or more unlicensed or inoperable vehicles is prohibited except in those districts where specified as an automobile wrecking yard or junk (or salvage) yard and allowed as a Permitted Use in Table 3-1 of the UDC, and such storage shall meet the requirements of UDC Section 4.10. In no case, shall any such unlicensed or inoperable vehiclesbe stored in an Environmentally Sensitive Area (ESA).
|
|
|
Title:
|
| | |
PARKING
|
|
Wording
|
| | |
A minimum of two (2) on-site parking spaces shall be provided for the single family residence.
|
|
|
Title:
|
| | |
Landslide Vegetative Buffer
|
|
Wording
|
| | |
A vegetative buffer of 30-feet shall be permanently maintained from the top or edge of the Landslide Hazard Area. All buffers shall be measured perpendicularly from the top of the Landslide Hazard Area.
|
|
|
Title:
|
| | |
Slide Buffer-Native Vegetation
|
|
Wording
|
| | |
Landslide Hazard Areas and their associated buffers shall remain naturally vegetated. Should buffer disturbance occur during construction, the Unified Development Code (UDC) Administrator shall require replanting with native vegetation. No alterations shall be made to the Landslide Hazard Area or its associated buffer without prior authorization by the UDC Administrator.
|
|
|
Title:
|
| | |
Identify Landslide Hazard Buffer
|
|
Wording
|
| | |
Prior to and during approved construction activities, the perimeter of the landslide hazard area buffer shall be marked with a temporary sign. The sign shall be placed in such a manner that it can be directly observed from the construction area. The sign shall contain the following statement: "Landslide Hazard Area and Buffer - Do not Remove or Alter Existing Vegetation."
|
|
|
Title:
|
| | |
Do Not Disturb Buffer
|
|
Wording
|
| | |
All construction activities shall not encroach upon the buffer. This includes the storage or preparation of materials.
|
|
|
Title:
|
| | |
Permanent Landslide Boundary
|
|
Wording
|
| | |
The applicant shall permanently separate the boundary of the Landslide Hazard Area Buffer from the remainder of the subject property through installing logs, trees, a hedge row, or any other prominent physical marking approved by the UDC Administrator.
|
|
|
Title:
|
| | |
Aquifer Recharge Conditions (SFR)
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
Stormwater Plan
|
|
Wording
|
| | |
A "Medium Project" Stormwater Site Plan has been submitted and approved by the Department of Community Development. Once the subject permit has been issued the applicant shall fully implement the provisions of the submitted plan and contact the Jefferson County Department of Community Development to arrange a schedule to inspect the property for plan compliance. A Certificate of Occupancy will not be issued until the Department verifies plan compliance. No clearing for roadways or utilities shall occur on the project site until clearing necessary for the installation of temporary sedimentation and erosion control measures have been completed.
|
|
|
Title:
|
| | |
PARCEL CREATED
|
|
Wording
|
| | |
The parcel was created through the Bruce B. Seton Short Plat on December 29, 1998 under AFN 417695.
|
|
|
Title:
|
| | |
DENSITY
|
|
Wording
|
| | |
The parcel has been designated as RR 1:20 under the Jefferson County Comprehensive Land Use Map effective August 28, 1998.
|
|
|
Title:
|
| | |
ACCESS/ADDRESS
|
|
Wording
|
| | |
The parcel has direct access via Totem Ridge Road, a private road (P530). An address of 625 Totem Ridge Road, Port Hadlock.
A road maintenance agreement has been recorded under AFN 417697, Vol. 631 Pages 254-258.
|
|
|
Title:
|
| | |
PARCEL HISTORY
|
|
Wording
|
| | |
A septic permit (SEP02-0287) was approved on December 20, 2002 for 600 GPD. A building permit (BLD03-0247) was issued on April 22, 2003 for a pole building. A FPA (FPA2605157) was finaled on April 16, 2003 for an uneven aged harvest. A well review (USR03-0036) was approved on August 11, 2003.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on August 26, 2003 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: landslide hazard area 1; SUSC aquifer recharge area.
|
|
|
Title:
|
| | |
F-Aquifer Recharge Area
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.
|
|
|
Title:
|
| | |
F-Susc. Aquifer Recharge Area
|
|
Wording
|
| | |
Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.
|
|
|
Title:
|
| | |
F-Geohazard Area
|
|
Wording
|
| | |
Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.
|
|
|
Title:
|
| | |
F-Adj. Mineral Land Disclosure
|
|
Wording
|
| | |
Jefferson County has determined that the use of certain properties for mineral resource extraction and processing activities is necessary to ensure resource availability in the County. The County will not consider to be a nuisance those inconveniences or discomforts arising from extraction and processing operations, if such operations are consistent with commonly acceped best management practices and comply with local, state, and federal laws. If your property is within five hundred (500) feet of property designated as Mineral Resource Land (MRL), you may be subject to inconveniences or discomforts arising from such operations, including but not limited to noise, tree removal, odors, fumes, dust, smoke, the operation of machinery, and the storage and disposal of aggegate products. One or more of the inconveniences described may occur as a result of extraction and processing operations which are in conformance with existing laws and regulations.
|
|
|
Title:
|
| | |
F-Stormwater
|
|
Wording
|
| | |
The applicant is proposing to create or add 4,300 square feet of impervious surface and 5,500 square feet of land disturbing activities.
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(b)(i).
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The revised site plan dated August 29, 2003 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated September 3, 2003 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for a single family residence with attached garage only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|