Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
1/24/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Building Inspection
|
|
Date Completed:
|
| | |
12/3/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Change Status to RENEWED
|
|
Date Completed:
|
| | |
10/7/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Foundation Inspection
|
|
Date Completed:
|
| | |
10/7/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
9/5/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
9/3/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
9/3/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-U
|
|
Date Completed:
|
| | |
9/2/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
8/26/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
8/5/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
8/1/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
8/26/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
8/1/2003
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
9/2/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
8/5/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
8/4/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
9/3/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
9/3/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
9/3/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
8/1/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Bld Setbacks
|
|
Wording
|
| | |
Minimum setback from Totem Ridge Road right-of-way shall be 20 feet. Minimum setback from Brookside Street right-of-way shall be 20 feet. Minimum side and rear setbacks shall be 5 feet. Minimum setback from easement right-of-way that provides access to Lots 1 & 2 of Van Trojen Short Plat (directly south) shall be 20 feet.
If ESA's are present then the more stricter setback shall apply.
|
|
|
Title:
|
| | |
Bld building height
|
|
Wording
|
| | |
The building height shall not exceed 35 feet.
|
|
|
Title:
|
| | |
Bld lot coverage
|
|
Wording
|
| | |
Maximum lot coverage shall not exceed 25%.
|
|
|
Title:
|
| | |
Outdoor Residential Storage
|
|
Wording
|
| | |
Outdoor residential storage shall be maintained in an orderly manner and shall create no fire, safety, health or sanitary hazard.
|
|
|
Title:
|
| | |
Unlicensed/Inoperable Vehicles
|
|
Wording
|
| | |
Not more than two (2) unlicensed or inoperable vehicles shall be stored on any lot less than one-half acre unless totally screened from view of neighboring dwellings and rights-of-way. Such screening shall meet all applicable performance and development standards specific to the district in which the storage is kept, and shall be in keeping with the character of the area. Screening shall meet the requirements of Unified Development Code (UDC) Section 6. Outdoor storage of thirteen (13) or more unlicensed or inoperable vehicles is prohibited except in those districts where specified as an automobile wrecking yard or junk (or salvage) yard and allowed as a Permitted Use in Table 3-1 of the UDC, and such storage shall meet the requirements of UDC Section 4.10. In no case, shall any such unlicensed or inoperable vehiclesbe stored in an Environmentally Sensitive Area (ESA).
|
|
|
Title:
|
| | |
Landslide Vegetative Buffer
|
|
Wording
|
| | |
A vegetative buffer of 30-feet shall be permanently maintained from the top or edge of the Landslide Hazard Area. All buffers shall be measured perpendicularly from the top of the Landslide Hazard Area.
|
|
|
Title:
|
| | |
Slide Buffer-Native Vegetation
|
|
Wording
|
| | |
Landslide Hazard Areas and their associated buffers shall remain naturally vegetated. Should buffer disturbance occur during construction, the Unified Development Code (UDC) Administrator shall require replanting with native vegetation. No alterations shall be made to the Landslide Hazard Area or its associated buffer without prior authorization by the UDC Administrator.
|
|
|
Title:
|
| | |
Identify Landslide Hazard Buffer
|
|
Wording
|
| | |
Prior to and during approved construction activities, the perimeter of the landslide hazard area buffer shall be marked with a temporary sign. The sign shall be placed in such a manner that it can be directly observed from the construction area. The sign shall contain the following statement: "Landslide Hazard Area and Buffer - Do not Remove or Alter Existing Vegetation."
|
|
|
Title:
|
| | |
Do Not Disturb Buffer
|
|
Wording
|
| | |
All construction activities shall not encroach upon the buffer. This includes the storage or preparation of materials.
|
|
|
Title:
|
| | |
Permanent Landslide Boundary
|
|
Wording
|
| | |
The applicant shall permanently separate the boundary of the Landslide Hazard Area Buffer from the remainder of the subject property through installing logs, trees, a hedge row, or any other prominent physical marking approved by the UDC Administrator.
|
|
|
Title:
|
| | |
Wetland Setback
|
|
Wording
|
| | |
A setback of 50-feet, measured perpendicularly from the wetland edge, shall be permanently maintained as a buffer. No filling, grading, clearing, or other alteration of the wetland or its buffer is allowed.
(Wetland delineation submitted at time of subdivision; SUB97-0014).
|
|
|
Title:
|
| | |
Identify Wetland Buffer
|
|
Wording
|
| | |
A permanent physical separation along the upland boundary of the wetland buffer area shall be installed and permanently maintained. Such separation can include installing logs, trees, a hedgerow, or any other prominent physical marking approved by the UDC Administrator.
|
|
|
Title:
|
| | |
Aquifer Recharge Conditions (SFR)
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
DENSITY
|
|
Wording
|
| | |
The parcel has been designated as RR 1:20 under the Jefferson County Comprehensive Land Use Plan effective August 28, 1998.
|
|
|
Title:
|
| | |
PARCEL CREATED
|
|
Wording
|
| | |
The parcel was created through the W.E. Seton Short Plat on December 29, 1998 under AFN 417696.
|
|
|
Title:
|
| | |
ACCESS/ADDRESS
|
|
Wording
|
| | |
Access to the parcel is provided via Totem Ridge Road, a private road (P530). An address of 222 Totem Ridge Road, Port Hadlock has been assigned to the parcel.
Brookside Street (a private road, P503) centerline abuts the western boundary of this parcel.
|
|
|
Title:
|
| | |
ROAD MAINTENANCE AGREEMENT
|
|
Wording
|
| | |
A road maintenance agreement for Totem Ridge Road has been recorded under AFN 417697. A road maintenance agreement for the private 30 foot ingress/egress easement adjacent to the western boundary was recorded on January 4, 1989 under AFN 319113.
|
|
|
Title:
|
| | |
GEOTECHNICAL REPORT NOT REQ'D
|
|
Wording
|
| | |
A geotechnical report was not required for the proposal.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on August 25, 2003 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: wetlands; seismic; landslide hazard area 1; SUSC aquifer recharge area.
|
|
|
Title:
|
| | |
F-Aquifer Recharge Area
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.
|
|
|
Title:
|
| | |
F-Susc. Aquifer Recharge Area
|
|
Wording
|
| | |
Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.
|
|
|
Title:
|
| | |
F-Adj. Mineral Land Disclosure
|
|
Wording
|
| | |
Jefferson County has determined that the use of certain properties for mineral resource extraction and processing activities is necessary to ensure resource availability in the County. The County will not consider to be a nuisance those inconveniences or discomforts arising from extraction and processing operations, if such operations are consistent with commonly acceped best management practices and comply with local, state, and federal laws. If your property is within five hundred (500) feet of property designated as Mineral Resource Land (MRL), you may be subject to inconveniences or discomforts arising from such operations, including but not limited to noise, tree removal, odors, fumes, dust, smoke, the operation of machinery, and the storage and disposal of aggegate products. One or more of the inconveniences described may occur as a result of extraction and processing operations which are in conformance with existing laws and regulations.
|
|
|
Title:
|
| | |
F-Stormwater
|
|
Wording
|
| | |
The applicant is proposing to create or add 480 square feet of impervious surface and 480 square feet of land disturbing activities.
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(b)(i).
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The site plan as submitted with the detached garage building permit application on July 30, 2003 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated September 3, 2003 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for a detached garage only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|