Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
1/12/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - FINAL FINAL Building
|
|
Date Completed:
|
| | |
8/9/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insp - Final Building
|
|
Date Completed:
|
| | |
8/9/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Failure to Schedule Inspection
|
|
Date Completed:
|
| | |
7/19/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Inspection Reminder Sent
|
|
Date Completed:
|
| | |
5/18/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Inspection Reminder Sent
|
|
Date Completed:
|
| | |
3/22/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Framing Inspection
|
|
Date Completed:
|
| | |
8/8/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Footing & Setback Inspection
|
|
Date Completed:
|
| | |
5/2/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Change Status to RENEWED
|
|
Date Completed:
|
| | |
5/5/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
4/22/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
4/21/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
4/21/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
4/21/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
4/21/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
4/18/2003
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
4/18/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
4/18/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
4/18/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
4/21/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
4/21/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
4/21/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
4/18/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
4/18/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
4/18/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Bld Setbacks
|
|
Wording
|
| | |
Totem Ridge Road is classified as private road and requires a minimum 20-foot road setback. All side and rear setbacks are maintaining a minimum 150-foot setback.
|
|
|
Title:
|
| | |
Bld building height
|
|
Wording
|
| | |
The building height is not to exceed 35 feet.
|
|
|
Title:
|
| | |
Bld lot coverage
|
|
Wording
|
| | |
Maximum lot coverage is not to exceed 25%. Lot coverage is defined by the amount of impervious surface which includes roof tops, concrete, gravel driveways, etc.
|
|
|
Title:
|
| | |
Landslide Vegetative Buffer
|
|
Wording
|
| | |
A vegetative buffer of 30-feet shall be permanently maintained from the top or edge of the Landslide Hazard Area. All buffers shall be measured perpendicularly from the top of the Landslide Hazard Area.
|
|
|
Title:
|
| | |
Slide Buffer-Native Vegetation
|
|
Wording
|
| | |
Landslide Hazard Areas and their associated buffers shall remain naturally vegetated. Should buffer disturbance occur during construction, the Unified Development Code (UDC) Administrator shall require replanting with native vegetation. No alterations shall be made to the Landslide Hazard Area or its associated buffer without prior authorization by the UDC Administrator.
|
|
|
Title:
|
| | |
Identify Landslide Hazard Buffer
|
|
Wording
|
| | |
Prior to and during approved construction activities, the perimeter of the landslide hazard area buffer shall be marked with a temporary sign. The sign shall be placed in such a manner that it can be directly observed from the construction area. The sign shall contain the following statement: "Landslide Hazard Area and Buffer - Do not Remove or Alter Existing Vegetation."
|
|
|
Title:
|
| | |
Do Not Disturb Buffer
|
|
Wording
|
| | |
All construction activities shall not encroach upon the buffer. This includes the storage or preparation of materials.
|
|
|
Title:
|
| | |
Permanent Landslide Boundary
|
|
Wording
|
| | |
The applicant shall permanently separate the boundary of the Landslide Hazard Area Buffer from the remainder of the subject property through installing logs, trees, a hedge row, or any other prominent physical marking approved by the UDC Administrator.
|
|
|
Title:
|
| | |
Aquifer Recharge Conditions (SFR)
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
Stormwater Plan
|
|
Wording
|
| | |
A Small Parcel Sedimentation and Erosion Control Plan has been submitted and approved by the Department of Community Development. Once the subject permit has been issued the applicant shall fully implement the provisions of the submitted plan and contact the Jefferson County Department of Community Development to arrange a schedule to inspect the property for plan compliance. A Certificate of Occupancy will not be issued until the Department verifies plan compliance. No clearing for roadways or utilities shall occur on the project site until clearing necessary for the installation of temporary sedimentation and erosion control measures have been completed.
|
|
|
Title:
|
| | |
F-Custom Universal Finding
|
|
Wording
|
| | |
This is for universal DRD findings. Not for custom case type specific findings.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on 4/18/03 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Landslide Hazard Area I (low), Susceptible Aquifer Recharge Area, and Stormwater.
|
|
|
Title:
|
| | |
F-Aquifer Recharge Area
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.
|
|
|
Title:
|
| | |
F-Susc. Aquifer Recharge Area
|
|
Wording
|
| | |
Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.
|
|
|
Title:
|
| | |
F-Geohazard Area
|
|
Wording
|
| | |
Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.
|
|
|
Title:
|
| | |
F-Stormwater
|
|
Wording
|
| | |
The applicant is proposing to create or add 4,750-square feet of impervious surface. Sections 6.6 and 6.7 of the Jefferson County Unified Development Code requires that your proposal submit a Small Parcel Sedimentation and Erosion Control Plan.
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The site plan as submitted with the building application on 4/17/03 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated 4/21/03 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for a Pole Building only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|