Description:
|
| | |
Miscellaneous Action
|
|
Date Completed:
|
| | |
1/12/2006
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Building Inspection
|
|
Date Completed:
|
| | |
2/17/2005
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Wallboard Inspection
|
|
Date Completed:
|
| | |
2/26/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insulation Inspection
|
|
Date Completed:
|
| | |
2/18/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Framing Inspection
|
|
Date Completed:
|
| | |
1/23/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Plumbing Inspection
|
|
Date Completed:
|
| | |
1/23/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Shear Wall Inspection
|
|
Date Completed:
|
| | |
11/14/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Insulation Inspection
|
|
Date Completed:
|
| | |
9/17/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Foundation Inspection
|
|
Date Completed:
|
| | |
9/17/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Foundation Inspection
|
|
Date Completed:
|
| | |
8/28/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Change Status to RENEWED
|
|
Date Completed:
|
| | |
8/20/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Footing & Setback Inspection
|
|
Date Completed:
|
| | |
8/19/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
4/18/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
4/18/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
4/18/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
4/4/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-U
|
|
Date Completed:
|
| | |
4/9/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
4/1/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
3/28/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
4/4/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
3/27/2003
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
4/17/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
4/14/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
4/18/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
4/4/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
4/4/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
4/18/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Bld Setbacks
|
|
Wording
|
| | |
Minimum setback from Bright Avenue right-of-way is 20 feet. Minimum setback from Lower Hadlock Road right-of-way is 20 feet. Minimum side yard setback is 5 feet. Minimum setback from OHWM is 30 feet.
|
|
|
Title:
|
| | |
Bld building height
|
|
Wording
|
| | |
The building height shall not exceed 35 feet.
|
|
|
Title:
|
| | |
PARKING
|
|
Wording
|
| | |
A minimum of two (2) on-site parking spaces shall be provided for the ADU.
|
|
|
Title:
|
| | |
Landslide Vegetative Buffer
|
|
Wording
|
| | |
A vegetative buffer of 30-feet shall be permanently maintained from the top or edge of the Landslide Hazard Area. All buffers shall be measured perpendicularly from the top of the Landslide Hazard Area.
|
|
|
Title:
|
| | |
Identify Landslide Hazard Buffer
|
|
Wording
|
| | |
Prior to and during approved construction activities, the perimeter of the landslide hazard area buffer shall be marked with a temporary sign. The sign shall be placed in such a manner that it can be directly observed from the construction area. The sign shall contain the following statement: "Landslide Hazard Area and Buffer - Do not Remove or Alter Existing Vegetation."
|
|
|
Title:
|
| | |
Do Not Disturb Buffer
|
|
Wording
|
| | |
All construction activities shall not encroach upon the buffer. This includes the storage or preparation of materials.
|
|
|
Title:
|
| | |
Permanent Landslide Boundary
|
|
Wording
|
| | |
The applicant shall permanently separate the boundary of the Landslide Hazard Area Buffer from the remainder of the subject property through installing logs, trees, a hedge row, or any other prominent physical marking approved by the UDC Administrator.
|
|
|
Title:
|
| | |
Aquifer Recharge Conditions (SFR)
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
Seawater Intrusion Areas
|
|
Wording
|
| | |
To help prevent seawater from intruding landward into underground aquifers, all new development activity on Marrowstone Island, Indian Island and within 1/4 mile of any marine shoreline shall be required to infiltrate all stormwater runoff onsite.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
DENSITY
|
|
Wording
|
| | |
The parcel has been designated as RR 1:5 under the Jefferson County Comprehensive Land Use Map effective August 28, 1998.
|
|
|
Title:
|
| | |
CASE HISTORY
|
|
Wording
|
| | |
A building permit (BLD01-0469) was finaled for a single family residence on May 17, 3001. A road approach permit (RAP01-0175) was finaled on June 21, 2002. A septic permit (SEP01-0083) was approved on August 22, 2001.
|
|
|
Title:
|
| | |
ROADS/ADDRESS
|
|
Wording
|
| | |
Brighton Avenue (C648909 and Lower Hadlock Road (C652509) are county local access roads.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on April 4, 2003 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: urban shoreline designation; landslide 1; SUSC aquifer recharge area; coastal SIPZ; seismic.
|
|
|
Title:
|
| | |
F-Aquifer Recharge Area
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.
|
|
|
Title:
|
| | |
F-Susc. Aquifer Recharge Area
|
|
Wording
|
| | |
Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.
|
|
|
Title:
|
| | |
F-Geohazard Area
|
|
Wording
|
| | |
Geologically Hazardous Areas in Jefferson County are characterized by slope, soil type, geologic material, and groundwater that may combine to create problems with slope stability, erosion, and water quality during and after construction or during natural events such as earthquakes or severe rainstorms.
|
|
|
Title:
|
| | |
F-SIPZ
|
|
Wording
|
| | |
Marine shorelines and islands are susceptible to a condition that is known as seawater intrusion. Seawater intrusion is a condition in which the saltwater/freshwater interface in an aquifer moves inland so that wells drilled on upland areas cannot obtain freshwater suitable for public consumption without significant additional treatment and cost. Maintaining a stable balance in the saltwater/freshwater interface is primarily a function of the rate of aquifer recharge (primarily through rainfall) and the rate of groundwater withdrawals (primarily through wells). The Washington Department of Ecology is the agency with statutory authority to regulate groundwater withdrawal for individual wells in Jefferson County. New development, redevelopment, and land use activities on islands and in close proximity to marine shorelines in particular should be developed in such a manner to maximize aquifer recharge and maintain the saltwater/freshwater balance to the maximum extent possible by infiltrating stormwater runoff so that it recharges the aquifer.
|
|
|
Title:
|
| | |
F-Coastal SIPZ
|
|
Wording
|
| | |
The parcel is located within a coastal SIPZ (seawater intrusion protection zone) according to the County GIS map. There are voluntary and mandatory measures identified in the Jefferson County Seawater Intrusion Policy (Resolution 44-22, effective September 23, 2002) that apply to well drilling proposals and building permit applications on existing lots of record.
A Coastal SIPZ is defined as: all islands and area within one-quarter mile of marine shoreline, but no history of chloride concentration above 100 mg/L in groundwater sources within 1000 feet.
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(b)(i).
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The revised site plan submitted on April 9, 2003 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated April 14, 2003 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for an addition and remodel to an ADU only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|