Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
12/7/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Plumbing/BLD Inspection
|
|
Date Completed:
|
| | |
3/19/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
SEPTIC system FINALED
|
|
Date Completed:
|
| | |
3/17/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
7/31/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
7/31/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
7/31/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
7/10/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
7/2/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
7/10/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
7/1/2002
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
7/31/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
7/11/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Potable Water Approval
|
|
Date Completed:
|
| | |
7/2/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
7/1/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
7/10/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
7/10/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
7/31/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
7/19/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
7/1/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Bld Setbacks
|
|
Wording
|
| | |
Minimum setback from Sycamore St is 20 feet. Minimum setback from Mason St is 20 feet. Minimum side and rear setbacks are 5 feet. All setbacks are to be measured from the property line.
|
|
|
Title:
|
| | |
Bld building height
|
|
Wording
|
| | |
The building height is not to exceed 35 feet.
|
|
|
Title:
|
| | |
Bld lot coverage
|
|
Wording
|
| | |
Maximum lot coverage is not to exceed 25%. Lot coverage is defined as area of impervious surface which includes rooftops, driveways, concrete, etc.
|
|
|
Title:
|
| | |
C-PARKING
|
|
Wording
|
| | |
A minimum of two on-site parking spaces are required for the single family residence with attached garage.
|
|
|
Title:
|
| | |
Aquifer Recharge Conditions (SFR)
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas may require special protection measures to mitigate water quality degradation. The submitted proposal does not require additional aquifer protection measures. However, during construction the project shall follow the Best Management Practices (BMPs) and facility design standards as identified and defined in the Stormwater Management Manual for the Puget Sound Basin.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
F-ZONING
|
|
Wording
|
| | |
This parcel has been designated as Rural Residential 1:5 under the Jefferson County Comprehensive Plan Land Use Map effective August 28, 1998.
|
|
|
Title:
|
| | |
F-RAP
|
|
Wording
|
| | |
Sycamore St (C642809) is a local access road. A road approach was reviewed under RAP02-00157. An address of 73 Sycamore St has been assigned to the parcel.
|
|
|
Title:
|
| | |
F-SEP
|
|
Wording
|
| | |
A septic permit (SEP02-00145) was issued July 11, 2002 for a system with capacity of 360 gallons per day. The cancelled septic applications (SEP94-00500 and SEP99-00066) have been filed with SEP02-00145.
|
|
|
Title:
|
| | |
F-SUB
|
|
Wording
|
| | |
This parcel was created through the Bishop Acres subdivision on March 19, 1990 and recorded under AFN 329172, Long Plats, Vol 16, pp 126-127.
|
|
|
Title:
|
| | |
F-EASEMENT
|
|
Wording
|
| | |
Per the Bishop Acres long plat as recorded under AFN 329172, "An easement is hereby reserved for and granted to Puget Sound Power and Light Company, US West, Port Townsend Cable T.V. Company, and their respective successors and assigns, under and upon the exterior 10 feet parallel with and adjoining the street frontage of all lots and tracts in which to install, lay, construct, renew, operate and maintain underground conduits, cable pipeline, and wires with the necessary facilities and other equipment for the purpose of service to this subdivision and other property with electric, telephone and cable T.V. service respectively, together with the right to enter upon the lots at all time for the purpose stated."
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on July 10, 2002 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Susceptible Aquifer Recharge Area, Special Aquifer Protection Area.
|
|
|
Title:
|
| | |
F-Aquifer Recharge Area
|
|
Wording
|
| | |
Aquifer Recharge Areas in Jefferson County are characterized by porous geological formations that allow percolation of the surface water into the soils and the underlying zone of saturation. Aquifers are geologic formations that contain sufficient saturated permeable material to yield significant quantities of water to wells and springs. Aquifers serve as the source of drinking water within most of the rural portions of Jefferson County.
|
|
|
Title:
|
| | |
F-Susc. Aquifer Recharge Area
|
|
Wording
|
| | |
Susceptible Aquifer Recharge Areas are those with geologic and hydrologic conditions that promote rapid infiltration of recharge waters to groundwater aquifers.
|
|
|
Title:
|
| | |
F-Critical Aquifer Recharge Area
|
|
Wording
|
| | |
Critical Aquifer Recharge Areas are defined as Seawater Intrusion Areas, and Special Aquifer Recharge Protection Areas and the following land uses located within Susceptible Aquifer Recharge Areas (1) All Industrial Land Uses (2) All Commercial Uses (3) All Rural Residential Land Uses requiring a Discretionary Use or Conditional Use Permit (4) All Rural Residential Land Uses with nonconforming uses that would otherwise require a Discretionary Use or Conditional Use Permit (5) Unsewered Planned Rural Residential Developments (6) Unsewered residential development with gross densities greater than one unit per acre. All of the above listed uses shall be subject to the applicable requirements and standards of the Jefferson County Unified Development Code.
|
|
|
Title:
|
| | |
F-Stormwater
|
|
Wording
|
| | |
The applicant is proposing to create or add 2,160 square feet of impervious surface and 4,100 square feet of land disturbing activities. Sections 6.6 and 6.7 of the Jefferson County Unified Development Code requires that your proposal adhere to Best Management Practices (BMPs).
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(b)(i).
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The site plan as submitted with the building application on June 28, 2002 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated July 19, 2002 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for a single family residence with attached garage only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|