Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
3/24/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Building Inspection
|
|
Date Completed:
|
| | |
1/6/2004
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Miscellaneous inspection
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Change Status to RENEWED
|
|
Date Completed:
|
| | |
7/2/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Miscellaneous inspection
|
|
Date Completed:
|
| | |
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Inspection Reminder Sent
|
|
Date Completed:
|
| | |
6/24/2003
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
7/3/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
6/26/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
6/25/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-U
|
|
Date Completed:
|
| | |
6/25/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-U
|
|
Date Completed:
|
| | |
6/14/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
3/29/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Additional Info Request-U
|
|
Date Completed:
|
| | |
5/16/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
3/29/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
3/21/2002
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
4/3/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
5/13/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Contractor License/Bond Info
|
|
Date Completed:
|
| | |
3/21/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
5/30/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
5/29/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
6/25/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
3/21/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Planning Appr
|
|
Date Completed:
|
| | |
7/1/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
DRD Approval (Zoning)
|
|
Date Completed:
|
| | |
6/25/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
3/21/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
3/21/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Bld Noise
|
|
Wording
|
| | |
The intensity of sound emitted by any commercial or industrial activity shall not exceed levels estabished by the Washington State Department of Ecology under WAC 173-60, and by Jefferson County under Resolution No. 67-85, "Establishment of Environmental Designations for Noise Abatement Areas for Jefferson County."
|
|
|
Title:
|
| | |
Bld Exterior height lights
|
|
Wording
|
| | |
Exterior lighting for commercial and industrial uses shall not exceed thirty feet (30') in height from the finished grade. Ground level lighting is encouraged.
|
|
|
Title:
|
| | |
Bld Lighted signs
|
|
Wording
|
| | |
Exterior lighting shall be energy-efficient and shielded or recessed so that direct glare and reflections are contained within the boundaries of the parcel. Exterior lighting shall be directed downward and away from adjoining properties and public rights-of way. No lighting shall blink, flash, or be of unusually high intensity or brightness. All lighting fixtures shall be appropriate in scale, intensity, and height to the use they are serving. Any lighting installed in parking areas shall be of direct cutoff design so that the source is not visible from adjacent property.
|
|
|
Title:
|
| | |
Bld Setbacks
|
|
Wording
|
| | |
Minimum setback from Ness' Corner Rd is 30 feet. Minimum side setbacks are 5 feet. Minimum rear setback (northern property line) is 35 feet.
|
|
|
Title:
|
| | |
Bld building height
|
|
Wording
|
| | |
The building height is not to exceed 35 feet.
|
|
|
Title:
|
| | |
Bld lot coverage
|
|
Wording
|
| | |
Maximum lot coverage is not to exceed 60%.
|
|
|
Title:
|
| | |
C-LANDSCAPING PLAN
|
|
Wording
|
| | |
The applicant shall comply with the approved landscaping plan dated June 25, 2002.
|
|
|
Title:
|
| | |
Stormwater Plan
|
|
Wording
|
| | |
A Small Parcel Erosion and Sediment Control Plan has been submitted and approved by the Department of Public Works. Once the subject permit has been issued the applicant shall fully implement the provisions of the submitted plan and contact the Jefferson County Department of Community Development to arrange a schedule to inspect the property for plan compliance. A Certificate of Occupancy will not be issued until the Department verifies plan compliance. No clearing for roadways or utilities shall occur on the project site until clearing necessary for the installation of temporary sedimentation and erosion control measures have been completed.
|
|
|
Title:
|
| | |
F-Custom Universal Finding
|
|
Wording
|
| | |
This parcel has been designated as Rural Village Center under the Jefferson County Comprehensive Plan Land Use Maps effective August 28, 1998.
|
|
|
Title:
|
| | |
F-Custom Universal Finding
|
|
Wording
|
| | |
Ness' Corner Rd (SR 116) is a major collector road. The road approach is existing, and an address of 901 Ness' Corner Rd has been assigned to the parcel.
|
|
|
Title:
|
| | |
F-CASE HISTORY
|
|
Wording
|
| | |
Permit history is as follows:
A building permit (BLD91-00134) for lumber storage was issued 3/15/91.
A building permit (BLD91-00456) for a 24x20 storage building was issued 7/1/91.
A building permit (BLD92-00086) for a 6,400 SF Retail Sales building was issued 2/25/92.
A building permit (BLD92-00141 for removal of a 500 gallon gas tank was issued 3/5/92.
A septic permit (SEP91-00146) was finaled 7/31/92.
A building permit (BLD93-00052) for a commercial addition with associated zoning review under IZ05-93 was finaled 12/21/93.
A building permit (BLD95-00451) for a temporary commercial mobile office was finaled 6/12/96 .
A building permit (BLD95-00667) for the New Store (Hadlock Building Supply) was finaled 5/29/96 .
A mechanical permit (BLD96-00065) was finaled 6/12/96.
A building permit (BLD96-00744) for a 10x32 addition was cancelled 12/2/97.
A building permit (BLD99-00122) for a commercial remodel was finaled 6/25/99.
A building permit (BLD99-00123) for a commercial addition was finaled 5/28/99.
A building permit (BLD01-00699) to enclose a covered load/unload area was issued 12/20/01.
|
|
|
Title:
|
| | |
F-PARKING
|
|
Wording
|
| | |
The exisitng development currently includes 54 parking spaces. No additional parking will be required at this time.
|
|
|
Title:
|
| | |
F-ZONING REVIEW
|
|
Wording
|
| | |
Zoning review was conducted and approved in 1991 for a lumber storage building under the Jefferson County Development Code (CC04-91). Zoning review was conducted and approved for a minor building expansion under the Jefferson County Comprehensive Plan, Tri-Area Community Plan, and the Jefferson County Emergency Zoning Ordinance (IZ05-93) on February 1, 1993.
|
|
|
Title:
|
| | |
F-No ESAs Found
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development for the presence of Environmentally Sensitive Areas (ESAs). The Department conducted a review and has concluded that the property DOES NOT contain Environmentally Sensitive Areas. However, future proposals will be subject to a new ESA review and conditions may be added if new ESAs are found on the property.
|
|
|
Title:
|
| | |
F-SEPA Exempt
|
|
Wording
|
| | |
Jefferson County determined that this proposal is categorically exempt from review under the State Environmental Policy Act (SEPA) pursuant to WAC 197-11-800(1)(b)(iii).
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The revised site plan as submitted with the building application on May 16, 2002 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated June 25, 2002 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|
|
Title:
|
| | |
F-Approval for _____ Only
|
|
Wording
|
| | |
This approval is for a pole building only. Any future permits on this site are subject to review for consistency with applicable codes and ordinances and does not preclude review and conditions which may be placed on future permits.
|
|