Case Number:BLD2001-00703 Case Status:Finaled Date Received:11/20/2001
Description:Stormwater Management Permit Date Issued:1/8/2002
Applicant: CENTURY TEL OF WASHINGTON Expiration Date:1/8/2003 12:00:00 AM
Site Address:CLEARWATER/HOH/SNAHAPISH MAINLINE ROAD R-O-W Case Finaled:4/12/2002
Parcel No:FRESH_SHOREOFSTATE Other Cases Parcel Data Map It More Details Parcels Images

Case Actions
Below is a list of actions that have been taken by staff for this permit case. They are sorted based on the date they were added to the database with most recent actions at the top. A value in the "Date Completed" field indicates that the action has been completed.
Description: File Archived
Date Completed: 12/18/2002
Disposition: DONE
Description: Set Status to F
Date Completed: 4/12/2002
Disposition: DONE
Description: Issue Building Permit (F)
Date Completed: 1/8/2002
Disposition: DONE
Description: Approve Permit-UF
Date Completed: 1/8/2002
Disposition: DONE
Description: App Substantially Complete-U
Date Completed: 12/21/2001
Disposition: DONE
Description: Case Entered
Date Completed: 12/21/2001
Disposition:
Description: Plan Check
Date Completed: 12/21/2001
Disposition: DONE
Description: Septic Review Complete-U
Date Completed: 12/21/2001
Disposition: DONE
Description: Potable Water Approval
Date Completed: 12/21/2001
Disposition: DONE
Description: Stormwater Review-U
Date Completed: 12/21/2001
Disposition: DONE
Description: Env. Sensitive Area Review-U
Date Completed: 12/21/2001
Disposition: DONE
Description: Consistency Review-U
Date Completed: 12/21/2001
Disposition: DONE
Description: RAP Review Complete-U
Date Completed: 12/21/2001
Disposition: DONE
Description: Det. of Completeness-UF
Date Completed: 12/21/2001
Disposition: DONE
Description: Print Dummy UDC Permit-UF
Date Completed: 12/21/2001
Disposition: DONE
Description: Review Complete-U
Date Completed: 12/21/2001
Disposition: DONE



Case Findings
Below is a list of findings for this permit case. Findings typically record facts that the staff are using as the basis of their permit processing decisions.
Title: F-Custom Universal Finding
Wording The proposed project is for the installation of 20-miles of fiber optic cable from the intersection of Highway 101 and the Clearwater/Hoh/Snahapish Mainline. The project has undergone extensive review through Shoreline Conditional Use Permit SDP01-00015. An open record hearing was held on 7/06/01 and a decision of approval was rendered by the Jefferson County Hearings Examiner.

Title: F-Custom Universal Finding
Wording In conjunction with the Shoreline Permit the applicant was required to submit a Stormwater Pollution Prevention Plan. The Plan was conducted by Murray Smith and Associates and reviewed by Jefferson County.

Title: F-Custom Universal Finding
Wording The Stormwater Pollution Prevention Plan has been reviewed and approved by the Jefferson County Department of Community Development. The applicant shall implement ALL proposed measures and follow the timing restrictions as identified in the plan.

Title: F-Confirmed ESAs
Wording The application was reviewed by the Jefferson County Department of Community Development staff on 4/19/01for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Shorelines, Type I Streams, and Wetlands.