Description:
|
| | |
Miscellaneous Action
|
|
Date Completed:
|
| | |
7/21/2011
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
File Archived
|
|
Date Completed:
|
| | |
12/18/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Final Plumbing/BLD Inspection
|
|
Date Completed:
|
| | |
6/18/2002
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Issue Building Permit (F)
|
|
Date Completed:
|
| | |
12/12/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Approve Permit-UF
|
|
Date Completed:
|
| | |
12/12/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Print Dummy UDC Permit-UF
|
|
Date Completed:
|
| | |
12/3/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Review Complete-U
|
|
Date Completed:
|
| | |
12/3/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Det. of Completeness-UF
|
|
Date Completed:
|
| | |
10/8/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Application Received-UF
|
|
Date Completed:
|
| | |
9/13/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
App Substantially Complete-U
|
|
Date Completed:
|
| | |
10/8/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Case Entered
|
|
Date Completed:
|
| | |
9/12/2001
|
|
Disposition:
|
| | |
|
|
|
Description:
|
| | |
Plan Check
|
|
Date Completed:
|
| | |
9/18/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Septic Review Complete-U
|
|
Date Completed:
|
| | |
11/29/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Stormwater Review-U
|
|
Date Completed:
|
| | |
11/28/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Env. Sensitive Area Review-U
|
|
Date Completed:
|
| | |
11/28/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Consistency Review-U
|
|
Date Completed:
|
| | |
11/28/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
RAP Review Complete-U
|
|
Date Completed:
|
| | |
9/12/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Description:
|
| | |
Building Permit Application(F)
|
|
Date Completed:
|
| | |
9/12/2001
|
|
Disposition:
|
| | |
DONE
|
|
|
Title:
|
| | |
Custom Universal Condition
|
|
Wording
|
| | |
The toilet facility must be pumped annually by October 31st. Following pumping of the facility it must be shut and locked for the entire flood season (November - February). The facility can reopen in March.
|
|
|
Title:
|
| | |
HOLD HARM RECRDED
|
|
Wording
|
| | |
The applicant has recorded the Hold Harmless Agreement which is available at the Jefferson County Auditors Office filed 11/27/01.
|
|
|
Title:
|
| | |
Res Construction Flood Damage
|
|
Wording
|
| | |
All new construction shall use construction methods which minimize flood damage.
|
|
|
Title:
|
| | |
Materials and Methods
|
|
Wording
|
| | |
All new construction shall: a. be anchored to prevent flotation, collapse, or lateral movement of the sturcture. b. be constructed with materials and utility equipment resistant to flood damage and potential damage to adjacent properties. c. be constructed using methods and practices that minimize flood damage. d. have structural components capable of resisting hydrostatic and hydrodynamic loads and the effects of buoyancy. e. electrical, heating, ventilation, plumbing, air-conditioning equipment, and other service facilities shall be designed and/or otherwise elevated or located so as to prevent water from entering or accumulating within the components during conditions of flooding.
|
|
|
Title:
|
| | |
Flood Proofing
|
|
Wording
|
| | |
Flood proofing of structures shall be provided by one or more of the following methods: a. Landfill: (Note: Landfills are not permitted in the floodway.) The placement of fill may be utilized to elevate the structure and must comply with the standards and policies of the Jefferson County Shoreline Master Program, if applicable. b. Pole, pier or piling construction: The use of poles, piers, or piles for the foundation of the structure may be used to allow the unrestricted flow of flood waters during periods at a base flood. The lowest floor must be one foot above the base flood level. c. Parallel Foundation Walls: Foundation walls may be designed and constructed to provide open spaces through which water can flow unrestricted to equalize pressure. In velocity flood situations, it is important that all foundation walls be parallel to the flow of the floodwaters. d. Extended Foundation Walls and Basements: (Note: Extended foundation walls and basements are not permitted in the floodway.) The lowest habitable floor of a residence may be constructed on foundation walls that extend above grade to one foot above the height of the base flood provided that residential construction complies with the requirment of Section 5.101(2), "Residential Construction," regarding the design of enclosed areas.
|
|
|
Title:
|
| | |
Utilities-Flood
|
|
Wording
|
| | |
Utilities shall be designed as specified in Section 5.20 of Ordinance No. 18-1120-95.
|
|
|
Title:
|
| | |
5-Foot Stream Setback
|
|
Wording
|
| | |
An additional setback of five (5) feet is required from the edge of the buffer area to the proposed vault toilet facility.
|
|
|
Title:
|
| | |
BMPs
|
|
Wording
|
| | |
The project shall adhere to the Best Management Practices (BMPs) to control stormwater, erosion and sediment during construction. BMPs shall address permanent measures to stabilize soil exposed during construction, and in the design and operation of stormwater and drainage control systems.
|
|
|
Title:
|
| | |
F-Custom Universal Finding
|
|
Wording
|
| | |
A Hold Harmless Indemnification Covenant was drafted for the septic and building permit. The Agreement outlines provisions for the placement of the vault toilet facility. In addition, The Jefferson County Flood Damage Prevention Ordinance (Ordinance No. 18-1120-95) identifies the responsibilities of the official. Such responsibilities include:
-Make interpretations where necessary and where possibleas to the exact location of boundaries of the areas of flood hazard.
-In the absence of detailed base flood elevation data sufficient to satisfy the requirements of this ordinance, the administrator shall obtain and consider the necessary information from federal, state, or other sources, to ensure that proposed construction will be reasonably safe from flooding. The test of reasonableness may include use of historical data, high water marks, and photographs of past flooding. Where deemed necessary, a determination by a professional engineer or surveyor may be required.
|
|
|
Title:
|
| | |
F-Custom Universal Finding
|
|
Wording
|
| | |
A mitigation plan was proposed by the Washington Department of Parks and Recreation which includes the following:
1. The applicant shall use the CXT Incorporated toilet facility.
2. The toilet must be closed and locked from November to March.
3. Prior to the toilet closure the facility must be pumped annually by October 31.
|
|
|
Title:
|
| | |
F-Confirmed ESAs
|
|
Wording
|
| | |
The application was reviewed by the Jefferson County Department of Community Development staff on 9/4/01 for the potential presence of Environmentally Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC). After an initial Geographic Information Systems mapping review and an investigative site inspection, the following ESAs were confirmed to be present on the subject property: Floodplain, and Type I Stream.
|
|
|
Title:
|
| | |
F-Streams
|
|
Wording
|
| | |
A Type 1 Stream (Fish and Wildlife Habitat Area) has been identified on the subject property. The stream will require a setback of 150-feet. The setback shall be measured horizontally from the Ordinary High Water Mark (OHWM). Fish and Wildlife Habitat Areas shall also have Buffers and Building Setbacks established.
|
|
|
Title:
|
| | |
F-Buffers
|
|
Wording
|
| | |
Buffers are areas that shall be maintained in their natural condition, however, minor pruning or alteration of vegetation may be permitted as long as the function and character of the buffer are not diminished.
|
|
|
Title:
|
| | |
F-Stormwater
|
|
Wording
|
| | |
The applicant is proposing to create or add 354 square feet of impervious surface. Sections 6.6 and 6.7 of the Jefferson County Unified Development Code requires that your proposal adhere to Best Management Practices (BMPs) to control sediment and erosion on the subject property.
|
|
|
Title:
|
| | |
F-Site Plan Changes
|
|
Wording
|
| | |
The site plan as submitted with the building/septic application on September 4, 2001 has been reviewed for consistency under the UDC, and has been approved by Jefferson County Department of Community Development. Any modifications, changes, and/or additions to the stamped, approved site plan dated 11/28/01 shall be resubmitted for review and approval by Jefferson County Department of Community Development.
|
|